  "family": "dc-siting",
  "generated": "2026-10-14",
  "note": "Real rows out of dated copies we sealed ourselves. Nothing here is made up.",
  "where_these_rows_came_from": "Where these rows came from, and anything their publisher requires to be printed alongside them, is set out on the page this file came from: https://ustechautomations.com/feeds/dc-siting",
  "rows_published": 25,
  "columns": 12,
  "headers": [
    "Datacenter named in the filing",
    "Company on the filing",
    "City",
    "State",
    "Agency list",
    "Case or permit number",
    "What this filing is for",
    "Where it has got to",
    "Date received",
    "Sealed copy",
    "What the agency's filing says",
    "Agency document"
  ],
  "rows": [
    [
      "ADC PLANO",
      "ALIGNED DATA CENTERS REIT LLC",
      "",
      "TX",
      "Texas air permit applications waiting on a decision",
      "131651",
      "Air permit for the site",
      "Technically Complete Application",
      "30 Mar 2026",
      "14 Oct 2026",
      "",
      "https://www.tceq.texas.gov/assets/public/permitting/air/reports/applications/407086-tc.pdf"
    ],
    [
      "GOODNIGHT DATA CENTER",
      "CRUSOE ENERGY SYSTEMS LLC",
      "",
      "TX",
      "Texas air permit applications waiting on a decision",
      "182880, GHGPSDTX268, PSDTX1698",
      "Air permit for the site",
      "Administrative Complete Application",
      "30 Jan 2026",
      "14 Oct 2026",
      "",
      "https://www.tceq.texas.gov/assets/public/permitting/air/reports/applications/404507-ac. pdf"
    ],
    [
      "LONGHORN DATA CENTER",
      "CRUSOE ENERGY SYSTEMS LLC",
      "",
      "TX",
      "Texas air permit applications waiting on a decision",
      "182126, GHGPSDTX263, PSDTX1688",
      "Air permit for the site",
      "Technically Complete Application",
      "7 Nov 2025",
      "14 Oct 2026",
      "",
      "https://www.tceq.texas.gov/assets/public/permitting/air/reports/applications/400428-tc.pdf"
    ],
    [
      "NEXUS DATA CENTER HUBBARD",
      "NEXUS HUBBARD POWER, LLC",
      "",
      "TX",
      "Texas air permit applications waiting on a decision",
      "183046, GHGPSDTX269, PSDTX1700",
      "Air permit for the site",
      "Administrative Complete Application",
      "17 Feb 2026",
      "14 Oct 2026",
      "",
      "https://www.tceq.texas.gov/assets/public/permitting/air/reports/applications/405217-ac. pdf"
    ],
    [
      "QTS - DFW 3 - DC1",
      "",
      "Lancaster",
      "TX",
      "FAA obstruction notices still open",
      "2026-ASW-15915-OE",
      "Building",
      "Studying",
      "23 Sep 2026",
      "1 Oct 2026",
      "Two level Data Center with support spaces.",
      ""
    ],
    [
      "QTS - DFW 3 - DC2",
      "",
      "Lancaster",
      "TX",
      "FAA obstruction notices still open",
      "2026-ASW-15916-OE",
      "Building",
      "Studying",
      "23 Sep 2026",
      "1 Oct 2026",
      "Two level Data Center with support spaces.",
      ""
    ],
    [
      "Transmission Tower 8",
      "",
      "snyder",
      "TX",
      "FAA obstruction notices still open",
      "2026-ASW-15931-OE",
      "Transmission line (t l tower)",
      "Studying",
      "23 Sep 2026",
      "1 Oct 2026",
      "This is a proposed pole location for a transmission line to feed the proposed Scurry County Data Center Project.",
      ""
    ],
    [
      "Transmission Tower 7",
      "",
      "snyder",
      "TX",
      "FAA obstruction notices still open",
      "2026-ASW-15932-OE",
      "Transmission line (t l tower)",
      "Studying",
      "23 Sep 2026",
      "1 Oct 2026",
      "This is a proposed pole location for a transmission line to feed the proposed Scurry County Data Center Project.",
      ""
    ],
    [
      "Transmission Tower 6",
      "",
      "snyder",
      "TX",
      "FAA obstruction notices still open",
      "2026-ASW-15933-OE",
      "Transmission line (t l tower)",
      "Studying",
      "23 Sep 2026",
      "1 Oct 2026",
      "This is a proposed pole location for a transmission line to feed the proposed Scurry County Data Center Project.",
      ""
    ],
    [
      "Transmission Tower 5",
      "",
      "snyder",
      "TX",
      "FAA obstruction notices still open",
      "2026-ASW-15934-OE",
      "Transmission line (t l tower)",
      "Studying",
      "23 Sep 2026",
      "1 Oct 2026",
      "This is a proposed pole location for a transmission line to feed the proposed Scurry County Data Center Project.",
      ""
    ],
    [
      "Transmission Tower 4",
      "",
      "snyder",
      "TX",
      "FAA obstruction notices still open",
      "2026-ASW-15935-OE",
      "Transmission line (t l tower)",
      "Studying",
      "23 Sep 2026",
      "1 Oct 2026",
      "This is a proposed pole location for a transmission line to feed the proposed Scurry County Data Center Project.",
      ""
    ],
    [
      "Transmission Tower 3",
      "",
      "snyder",
      "TX",
      "FAA obstruction notices still open",
      "2026-ASW-15936-OE",
      "Transmission line (t l tower)",
      "Studying",
      "23 Sep 2026",
      "1 Oct 2026",
      "This is a proposed pole location for a transmission line to feed the proposed Scurry County Data Center Project.",
      ""
    ],
    [
      "Transmission Tower 2",
      "",
      "snyder",
      "TX",
      "FAA obstruction notices still open",
      "2026-ASW-15937-OE",
      "Transmission line (t l tower)",
      "Studying",
      "23 Sep 2026",
      "1 Oct 2026",
      "This is a proposed pole location for a transmission line to feed the proposed Scurry County Data Center Project.",
      ""
    ],
    [
      "Transmission Tower 1",
      "",
      "snyder",
      "TX",
      "FAA obstruction notices still open",
      "2026-ASW-15938-OE",
      "Transmission line (t l tower)",
      "Studying",
      "23 Sep 2026",
      "1 Oct 2026",
      "This is a proposed pole location for a transmission line to feed the proposed Scurry County Data Center Project.",
      ""
    ],
    [
      "Belmont Building 5",
      "",
      "Leesburg",
      "VA",
      "FAA obstruction notices still open",
      "2026-AEA-11315-OE",
      "Crane",
      "Studying",
      "22 Sep 2026",
      "1 Oct 2026",
      "Use a crane to erect the structural steel for a new 4 story data center which is 100' tall.",
      ""
    ],
    [
      "Ironwood Building ARK3",
      "",
      "Clarksville",
      "AR",
      "FAA obstruction notices still open",
      "2026-ASW-15894-OE",
      "Building",
      "Studying",
      "22 Sep 2026",
      "1 Oct 2026",
      "Structure Type: Two-Story Data Center with Rooftop Mechanical Equipment Overall Footprint: 650 feet (length) x 450 feet (width) Building Use: Mission-critical data processing facility (data center) with associated mechanical electrical and cooling infrastructure. Number of Stories: 2 stories above finished grade. Primary Construction: Structural steel framing with reinforced concrete foundations and composite metal deck floor system. Exterior envelope consists of insulated metal wall panels and precast concrete wall \\npanels. Rooftop Equipment: The roof will support mechanical and electrical equipment associated with data center operations including: Air-handling units (AHUs) Cooling towers or dry coolers Condenser units Electrical equipment and associated screening structures Piping racks and service platforms Maintenance access walkways and guardrails All rooftop \\nequipment will be mounted on structural steel dunnage frames anchored to the building structure. Approximate Height: Building roof height: -40-45 feet above finished grade Rooftop equipment height: approximately 10-20 feet above roof surface Total overall height: approximately 55-65 feet above finished grade Roof Type: Flat roof with parapet and internal drainage system. Site Context: The structure will be located within a secured industrial campus and is part of a larger data center development consisting of multiple buildings electrical yards and support infrastructure. Lighting: Structure will not require obstruction lighting unless determined necessary by the FAA during aeronautical evaluation.",
      ""
    ],
    [
      "IAD56 Filigree Court",
      "",
      "Ashburn",
      "VA",
      "FAA obstruction notices still open",
      "2026-AEA-11157-OE",
      "Crane",
      "Studying",
      "18 Sep 2026",
      "1 Oct 2026",
      "The scope of work contained in this package of drawings is the Shell Core and Power Base Building Interior for the IAD56 Data Center located in Ashburn Virginia. Work includes new construction mechanical plumbing and electrical systems.",
      ""
    ],
    [
      "Silverbrook Center",
      "",
      "Sterling",
      "VA",
      "FAA obstruction notices still open",
      "2026-AEA-11111-OE",
      "Building",
      "Studying",
      "17 Sep 2026",
      "1 Oct 2026",
      "Proposed data center building",
      ""
    ],
    [
      "Silverbrook Center",
      "",
      "Sterling",
      "VA",
      "FAA obstruction notices still open",
      "2026-AEA-11113-OE",
      "Building",
      "Studying",
      "17 Sep 2026",
      "1 Oct 2026",
      "Proposed data center building",
      ""
    ],
    [
      "2 antennas for AWS data center time sync",
      "",
      "Manassas",
      "VA",
      "FAA obstruction notices still open",
      "2026-AEA-10995-OE",
      "Tower (non)",
      "Evaluating",
      "14 Sep 2026",
      "1 Oct 2026",
      "Antenna mast attached to concrete parapet wall on building roof with pipe clamp connected to unistrut. GPS antenna attached to top of antenna mast with pipe mount adapter.",
      ""
    ],
    [
      "Crane_D_Point_5",
      "",
      "Fairfax County",
      "VA",
      "FAA obstruction notices still open",
      "2026-AEA-9982-OE",
      "Crane",
      "Evaluating",
      "21 Aug 2026",
      "1 Oct 2026",
      "275ft Mobile Crane being used for Construction of (2) 130ft AGL; 451ft AMSL Data Center Buildings located in Fairfax County Virginia. Permaneat structure ASN: 2023-AEA-7476-THRU-7484-OE",
      ""
    ],
    [
      "Crane_D_Point_6",
      "",
      "Fairfax County",
      "VA",
      "FAA obstruction notices still open",
      "2026-AEA-9983-OE",
      "Crane",
      "Evaluating",
      "21 Aug 2026",
      "1 Oct 2026",
      "275ft AGL Mobile Crane being used for Construction of (2) 130ft AGL; 451ft AMSL Data Center Buildings located in Fairfax County Virginia. Permaneat structure ASN: 2023-AEA-7476-THRU-7484-OE",
      ""
    ],
    [
      "Crane_D_Point_7",
      "",
      "Fairfax County",
      "VA",
      "FAA obstruction notices still open",
      "2026-AEA-9985-OE",
      "Crane",
      "Evaluating",
      "21 Aug 2026",
      "1 Oct 2026",
      "275ft AGL Mobile Crane being used for Construction of (2) 130ft AGL; 451ft AMSL Data Center Buildings located in Fairfax County Virginia. Permaneat structure ASN: 2023-AEA-7476-THRU-7484-OE",
      ""
    ],
    [
      "Crane_D_Point_8",
      "",
      "Fairfax County",
      "VA",
      "FAA obstruction notices still open",
      "2026-AEA-9986-OE",
      "Crane",
      "Evaluating",
      "21 Aug 2026",
      "1 Oct 2026",
      "275ft Mobile Crane being used for Construction of (2) 130ft AGL; 451ft AMSL Data Center Buildings located in Fairfax County Virginia. Permaneat structure ASN: 2023-AEA-7476-THRU-7484-OE",
      ""
    ],
    [
      "IAD48 Shell and PBB",
      "",
      "Sterling",
      "VA",
      "FAA obstruction notices still open",
      "2026-AEA-9917-OE",
      "Building (commercial)",
      "Studying",
      "20 Aug 2026",
      "1 Oct 2026",
      "This building will be a 2-story data center",
      ""
    ]
  ]
}