 "blogId": "D0383",
 "slug": "colorado-interconnection-queue",
 "title": "What Is Queued to Connect in Colorado?",
 "template": "R11_GRID_STATE_REPORT",
 "editionId": "2026-07",
 "snapshotSha256": "83af023cf9658e7b563d7b40f5186ff6889c0e5695bfeb5cfa027a2950889a15",
 "sealedAt": "2026-07-09T20:21:26.330Z",
 "source": "US Tech Automations Research",
 "methodology": "https://ustechautomations.com/resources/research",
 "canonicalUrl": "https://ustechautomations.com/resources/blog/colorado-interconnection-queue",
 "displays": [
  {
   "key": "state.CO.name",
   "display": "Colorado",
   "value": null,
   "kind": "label"
  },
  {
   "key": "state.CO.code",
   "display": "CO",
   "value": null,
   "kind": "label"
  },
  {
   "key": "state.CO.projects",
   "display": "78",
   "value": 78,
   "kind": "count"
  },
  {
   "key": "state.CO.capacityMw",
   "display": "14,011 MW",
   "value": 14011,
   "kind": "capacity"
  },
  {
   "key": "state.CO.capacityGw",
   "display": "14.0 GW",
   "value": null,
   "kind": "capacity"
  },
  {
   "key": "state.CO.medianMw",
   "display": "189 MW",
   "value": null,
   "kind": "capacity"
  },
  {
   "key": "state.CO.status.withdrawn",
   "display": "0",
   "value": 0,
   "kind": "count"
  },
  {
   "key": "state.CO.status.withdrawnPct",
   "display": "0.0%",
   "value": null,
   "kind": "percent"
  },
  {
   "key": "state.CO.status.inQueue",
   "display": "74",
   "value": 74,
   "kind": "count"
  },
  {
   "key": "state.CO.status.inQueuePct",
   "display": "94.9%",
   "value": null,
   "kind": "percent"
  },
  {
   "key": "state.CO.status.operational",
   "display": "4",
   "value": 4,
   "kind": "count"
  },
  {
   "key": "state.CO.largest.mw",
   "display": "500 MW",
   "value": 500,
   "kind": "capacity"
  },
  {
   "key": "state.CO.fuel.hybrid.count",
   "display": "22",
   "value": 22,
   "kind": "count"
  },
  {
   "key": "state.CO.fuel.hybrid.capacityMw",
   "display": "4,414 MW",
   "value": 4414,
   "kind": "capacity"
  },
  {
   "key": "state.CO.fuel.hybrid.label",
   "display": "Hybrid",
   "value": null,
   "kind": "label"
  },
  {
   "key": "state.CO.fuel.wind.count",
   "display": "20",
   "value": 20,
   "kind": "count"
  },
  {
   "key": "state.CO.fuel.wind.capacityMw",
   "display": "3,976 MW",
   "value": 3976,
   "kind": "capacity"
  },
  {
   "key": "state.CO.fuel.wind.label",
   "display": "Wind",
   "value": null,
   "kind": "label"
  },
  {
   "key": "state.CO.fuel.solar.count",
   "display": "18",
   "value": 18,
   "kind": "count"
  },
  {
   "key": "state.CO.fuel.solar.capacityMw",
   "display": "2,848 MW",
   "value": 2848,
   "kind": "capacity"
  },
  {
   "key": "state.CO.fuel.solar.label",
   "display": "Solar",
   "value": null,
   "kind": "label"
  },
  {
   "key": "state.CO.fuel.battery-storage.count",
   "display": "14",
   "value": 14,
   "kind": "count"
  },
  {
   "key": "state.CO.fuel.battery-storage.capacityMw",
   "display": "1,734 MW",
   "value": 1734,
   "kind": "capacity"
  },
  {
   "key": "state.CO.fuel.battery-storage.label",
   "display": "Battery Storage",
   "value": null,
   "kind": "label"
  },
  {
   "key": "state.CO.fuel.natural-gas.count",
   "display": "4",
   "value": 4,
   "kind": "count"
  },
  {
   "key": "state.CO.fuel.natural-gas.capacityMw",
   "display": "1,039 MW",
   "value": 1039,
   "kind": "capacity"
  },
  {
   "key": "state.CO.fuel.natural-gas.label",
   "display": "Natural Gas",
   "value": null,
   "kind": "label"
  },
  {
   "key": "state.CO.fuel.top.label",
   "display": "Hybrid",
   "value": null,
   "kind": "label"
  },
  {
   "key": "state.CO.fuel.top.sharePct",
   "display": "28.2%",
   "value": null,
   "kind": "percent"
  },
  {
   "key": "state.CO.topPeer.label",
   "display": "SPP",
   "value": null,
   "kind": "label"
  },
  {
   "key": "state.CO.topPeer.projects",
   "display": "78",
   "value": 78,
   "kind": "count"
  },
  {
   "key": "edition.snapshotDate",
   "display": "July 9, 2026",
   "value": null,
   "kind": "window"
  },
  {
   "key": "edition.isos",
   "display": "6",
   "value": 6,
   "kind": "count"
  },
  {
   "key": "edition.states",
   "display": "36",
   "value": 36,
   "kind": "count"
  },
  {
   "key": "edition.methodology.fuelBucketing",
   "display": "Vendor fuel and technology labels differ by ISO and are grouped into Solar, Battery Storage, Wind, Natural Gas, Hybrid and Other by keyword.",
   "value": null,
   "kind": "note"
  },
  {
   "key": "edition.methodology.statusBucketing",
   "display": "Each ISO publishes its own status taxonomy; statuses are grouped into withdrawn, operational (explicitly in-service or commercial operation), still-in-queue, and unknown for feeds that publish no status. Some ISOs drop withdrawn projects from their feed entirely.",
   "value": null,
   "kind": "note"
  },
  {
   "key": "edition.projects",
   "display": "12,260",
   "value": 12260,
   "kind": "count"
  },
  {
   "key": "edition.capacityMw",
   "display": "1,945,749 MW",
   "value": 1945749,
   "kind": "capacity"
  },
  {
   "key": "edition.capacityGw",
   "display": "1945.7 GW",
   "value": null,
   "kind": "capacity"
  },
  {
   "key": "edition.medianMw",
   "display": "148 MW",
   "value": null,
   "kind": "capacity"
  },
  {
   "key": "edition.status.withdrawn",
   "display": "5,341",
   "value": 5341,
   "kind": "count"
  },
  {
   "key": "edition.status.withdrawnPct",
   "display": "43.6%",
   "value": null,
   "kind": "percent"
  },
  {
   "key": "edition.status.inQueue",
   "display": "4,882",
   "value": 4882,
   "kind": "count"
  },
  {
   "key": "edition.status.inQueuePct",
   "display": "39.8%",
   "value": null,
   "kind": "percent"
  },
  {
   "key": "edition.status.operational",
   "display": "290",
   "value": 290,
   "kind": "count"
  },
  {
   "key": "edition.status.unknown",
   "display": "1,747",
   "value": 1747,
   "kind": "count"
  },
  {
   "key": "edition.status.unknownPct",
   "display": "14.2%",
   "value": null,
   "kind": "percent"
  },
  {
   "key": "edition.status.withdrawnPctOfKnown",
   "display": "50.8%",
   "value": null,
   "kind": "percent"
  },
  {
   "key": "edition.largest.mw",
   "display": "3,200 MW",
   "value": 3200,
   "kind": "capacity"
  },
  {
   "key": "edition.largest.name",
   "display": "ATLAS COMPLEX",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.solar.count",
   "display": "4,149",
   "value": 4149,
   "kind": "count"
  },
  {
   "key": "edition.fuel.solar.capacityMw",
   "display": "515,158 MW",
   "value": 515158,
   "kind": "capacity"
  },
  {
   "key": "edition.fuel.solar.label",
   "display": "Solar",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.battery-storage.count",
   "display": "2,826",
   "value": 2826,
   "kind": "count"
  },
  {
   "key": "edition.fuel.battery-storage.capacityMw",
   "display": "442,540 MW",
   "value": 442540,
   "kind": "capacity"
  },
  {
   "key": "edition.fuel.battery-storage.label",
   "display": "Battery Storage",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.other.count",
   "display": "2,471",
   "value": 2471,
   "kind": "count"
  },
  {
   "key": "edition.fuel.other.capacityMw",
   "display": "408,648 MW",
   "value": 408648,
   "kind": "capacity"
  },
  {
   "key": "edition.fuel.other.label",
   "display": "Other",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.wind.count",
   "display": "1,720",
   "value": 1720,
   "kind": "count"
  },
  {
   "key": "edition.fuel.wind.capacityMw",
   "display": "319,023 MW",
   "value": 319023,
   "kind": "capacity"
  },
  {
   "key": "edition.fuel.wind.label",
   "display": "Wind",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.natural-gas.count",
   "display": "555",
   "value": 555,
   "kind": "count"
  },
  {
   "key": "edition.fuel.natural-gas.capacityMw",
   "display": "196,076 MW",
   "value": 196076,
   "kind": "capacity"
  },
  {
   "key": "edition.fuel.natural-gas.label",
   "display": "Natural Gas",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.hybrid.count",
   "display": "482",
   "value": 482,
   "kind": "count"
  },
  {
   "key": "edition.fuel.hybrid.capacityMw",
   "display": "53,729 MW",
   "value": 53729,
   "kind": "capacity"
  },
  {
   "key": "edition.fuel.hybrid.label",
   "display": "Hybrid",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.hydro.count",
   "display": "24",
   "value": 24,
   "kind": "count"
  },
  {
   "key": "edition.fuel.hydro.capacityMw",
   "display": "5,086 MW",
   "value": 5086,
   "kind": "capacity"
  },
  {
   "key": "edition.fuel.hydro.label",
   "display": "Hydro",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.nuclear.count",
   "display": "24",
   "value": 24,
   "kind": "count"
  },
  {
   "key": "edition.fuel.nuclear.capacityMw",
   "display": "2,374 MW",
   "value": 2374,
   "kind": "capacity"
  },
  {
   "key": "edition.fuel.nuclear.label",
   "display": "Nuclear",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.coal.count",
   "display": "9",
   "value": 9,
   "kind": "count"
  },
  {
   "key": "edition.fuel.coal.capacityMw",
   "display": "3,115 MW",
   "value": 3115,
   "kind": "capacity"
  },
  {
   "key": "edition.fuel.coal.label",
   "display": "Coal",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.top.label",
   "display": "Solar",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.fuel.top.sharePct",
   "display": "33.8%",
   "value": null,
   "kind": "percent"
  },
  {
   "key": "edition.topPeer.label",
   "display": "MISO",
   "value": null,
   "kind": "label"
  },
  {
   "key": "edition.topPeer.projects",
   "display": "3,792",
   "value": 3792,
   "kind": "count"
  }
 ]
}