Datacenter regulatory-trace changes as of September 1, 2026

As of 2026-09-01, 10 of the 57 tracked announced sites had a changed phantom score, or entered the baseline, in this published comparison.

Compared with the immediately preceding sealed source report dated 2026-08-31. The score reports how much trace was observed in bounded public air-permit and FAA airspace sources. A higher score is a diligence prompt, not a verdict about whether a datacenter will be built.

472permit applications in the source snapshot
28,679non-terminal FAA cases observed nationally
8.0 kmfixed airspace join radius

Sites that define this dated page

Announced sitePrior scoreCurrent scoreObserved trace
AWS Richmond County Campus (Energy Way Industrial Park)
Amazon · Hamlet, Richmond County, NC
3050No bounded trace observed
AWS Ridgeland (Costas property) Campus
Amazon · Ridgeland, MS
3020FAA cases within 8.0km x7; active construction (4 crane cases)
Google Council Bluffs (East)
Google · Council Bluffs, IA
3020FAA cases within 8.0km x2; active construction (1 crane cases)
Google Fort Wayne Data Center
Google · Fort Wayne, IN
3020FAA cases within 8.0km x3; active construction (2 crane cases)
Google Kansas City (East)
Google · Kansas City, MO
2030FAA cases within 8.0km x2
Google Lincoln Data Center
Google · Lincoln, NE
5030FAA cases within 8.0km x1
Google Omaha Data Center
Google · Omaha, NE
2030FAA cases within 8.0km x1
Microsoft Fairwater Atlanta
Microsoft · Fayetteville/South Fulton, GA
5030FAA cases within 8.0km x1
Nebius/DataOne Vineland Campus
Nebius/DataOne · Vineland, Cumberland County, NJ
5030FAA cases within 8.0km x1
xAI Colossus 1 (former Electrolux plant)
xAI · Memphis, TN
5020FAA cases within 8.0km x2; active construction (2 crane cases)

Rows not shown retained the same score and are intentionally omitted. That keeps this page about what changed instead of reproducing a 57-row table every day. Score bands are heuristic and depend on coverage: TCEQ pending applications cover Texas, while the FAA case layer is national. An issued permit, a local permit outside the collected sources, or construction that needs no sampled FAA filing can all be absent from this view.

Method, source, and content seal

The September 1, 2026 comparison is derived from public records published by TCEQ and the FAA Part 77 archive. The scorer joins those bounded records to publicly announced site locations. Name-token matches that are merely contextual do not count as direct permit evidence. Distance matches use the fixed radius shown above. The method does not infer power, capacity, financing, completion, or operator intent.

The September 1, 2026 source artifact reproduced its declared SHA-256 seal before this response was rendered. The seal excludes only the machine-local database path; dates, source counts, site rows, scores, and reasons remain bound.

SHA-256: 70e97dd11a9d7f673e2fe48c9ffac017915c9548abc9e2c2ed894a500fe9e8fe