Interconnection queue › Michigan › Solar
Snapshot of 2026-07-30 · 247 projects
247 solar projects are in the interconnection queue with a Michigan location, totalling 20,239 MW across the 247 that publish a capacity.
Get told what moves in solar in Michigan
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in solar in Michigan: what entered, what moved study phase, what came off the list.
Email me solar in Michigan queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| MISO | 247 | 20,239 MW |
| Status | Projects |
|---|---|
| Withdrawn | 120 |
| Active | 64 |
| Done | 41 |
| Pending Revision Approval | 21 |
| LEGACY: Done | 1 |
| County | Projects | Capacity |
|---|---|---|
| Bay | 11 | 385 MW |
| Saginaw | 8 | 845 MW |
| Sanilac | 8 | 1,120 MW |
| Monroe | 7 | 385 MW |
| Midland | 7 | 304 MW |
| Livingston | 6 | 445 MW |
| Washtenaw County | 6 | 559 MW |
| Shiawassee County | 6 | 729 MW |
| Dickinson | 6 | 142 MW |
| Tuscola | 5 | 405 MW |
| Hillsdale | 5 | 470 MW |
| Lenawee | 5 | 175 MW |
| Mason | 5 | 658 MW |
| Eaton County | 5 | 250 MW |
| Calhoun County | 5 | 674 MW |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| MISO | 2026-07-30 | 2026-07-30 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.