US Interconnection Queue Tracker

12,327 projects across 6 ISOs, snapshot of 2026-07-30 · re-read every week since 2026-06-11 · the ISOs keep no archive, so the history here cannot be recovered anywhere else.

Between 2026-07-23 and 2026-07-30 we recorded 6 new queue entries, 118 status changes and 0 projects no longer listed. See what moved →

By ISO

ISOProjectsCapacityStatesPublishes status?
MISO (Midcontinent ISO)3,801299,541 MW16yes
CAISO (California ISO)2,278492,197 MW7yes
ERCOT (Texas)1,839426,814 MW1yes
ISO-NE (New England)1,747193,097 MW (from 1,471 of 1,747 projects)8not in this report
NYISO (New York ISO)1,637344,914 MW (from 1,480 of 1,637 projects)5yes
SPP (Southwest Power Pool)1,025192,920 MW15yes

By technology

The six ISOs use six different fuel vocabularies, so this table — and only this table — maps them onto shared buckets. Anything we could not map from the ISO's own published coding is counted as unclassified rather than guessed at (2,537 projects). Per-ISO pages show the raw vocabulary instead.

TechnologyProjectsCapacity
Solar4,250514,017 MW (from 4,245 of 4,250 projects)
Storage2,239319,586 MW (from 2,235 of 2,239 projects)
Hybrid60253,140 MW
Wind1,430332,412 MW (from 1,421 of 1,430 projects)
Gas829247,253 MW (from 793 of 829 projects)
Hydro10011,931 MW (from 96 of 100 projects)
Nuclear272,487 MW (from 22 of 27 projects)
Geothermal352,966 MW
Biomass & waste791,159 MW (from 63 of 79 projects)
Oil & diesel22882 MW (from 15 of 22 projects)
Coal113,140 MW
Transmission16655,588 MW (from 62 of 166 projects)
Unclassified2,537404,922 MW (from 2,294 of 2,537 projects)

Get told what moves in your market

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in your market: what entered, what moved study phase, what came off the list.

Email me my market's queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By state

Also present, below our page threshold: MX (18), Wyoming (14), New Jersey (8), Montana (3), Idaho (2), Alaska (1), NB (1), Delaware (1).

Where each number came from

Read this before quoting a figure. We re-read every source every week, but a weekly read of an unchanged file is not weekly data. These have not moved in a while: ERCOT last changed 2026-06-11 (9 identical reads since); NYISO last changed 2026-07-16 (3 identical reads since). Those rows are exactly as current as the ISO's own published file, and no more.
ISOWe last readSource last changedSource
CAISO2026-07-302026-07-30 (changed this snapshot)source file
ERCOT2026-07-302026-06-11 (unchanged across 9 weekly reads)source file
ISO-NE2026-07-302026-07-30 (changed this snapshot)source file
MISO2026-07-302026-07-30 (changed this snapshot)source file
NYISO2026-07-302026-07-16 (unchanged across 3 weekly reads)source file
SPP2026-07-302026-07-30 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.

Interconnection queue home · This week's changes · How this is collected · US Tech Automations.