US Interconnection Queue Tracker
6,687 projects across 4 ISOs, snapshot of 2026-09-07 · re-read every week since 2026-06-11 · the ISOs keep no archive, so the history here cannot be recovered anywhere else.
Between 2026-09-06 and 2026-09-07 we recorded 0 new queue entries, 0 status changes, and 0 projects no longer listed. See what moved →
By ISO
| ISO | Projects | Capacity | States | Publishes status? |
|---|---|---|---|---|
| CAISO (California ISO) | 2,278 | 492,197 MW | 7 | yes |
| ISO-NE (New England) | 1,747 | 193,097 MW | 8 | not in this report |
| NYISO (New York ISO) | 1,638 | 344,904 MW | 5 | yes |
| SPP (Southwest Power Pool) | 1,024 | 191,865 MW | 15 | yes |
By technology
Each ISO uses its own fuel vocabulary, so this table, and only this table, maps them onto shared buckets. Anything we could not map from the ISO's own published coding is counted as unclassified rather than guessed at (1,370 projects). Per-ISO pages show the raw vocabulary instead.
| Technology | Projects | Capacity |
|---|---|---|
| Solar | 1,850 | 217,048 MW |
| Storage | 1,501 | 280,511 MW |
| Hybrid | 228 | 21,111 MW |
| Wind | 749 | 233,455 MW |
| Gas | 583 | 154,354 MW |
| Hydro | 93 | 10,556 MW |
| Nuclear | 18 | 424 MW |
| Geothermal | 35 | 2,966 MW |
| Biomass & waste | 73 | 1,120 MW |
| Oil & diesel | 15 | 717 MW |
| Coal | 9 | 3,115 MW |
| Transmission | 163 | 55,588 MW |
| Unclassified | 1,370 | 241,098 MW |
See what moved in your market each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in your market, from new entries to projects that came off the list.
Email me my market's queue changesWork email only. No newsletter, no obligation.
By state
- California
- New York
- Massachusetts
- Maine
- Connecticut
- Oklahoma
- Kansas
- New Hampshire
- Rhode Island
- Nebraska
- Texas
- Vermont
- Nevada
- Colorado
- Arizona
- Missouri
- New Mexico
- Pennsylvania
- North Dakota
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| CAISO | 2026-09-07 | 2026-09-07 | source file |
| ISO-NE | 2026-09-07 | 2026-09-07 | source file |
| NYISO | 2026-09-07 | 2026-08-13 | source file |
| SPP | 2026-09-07 | 2026-09-05 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.