Interconnection queue › Michigan › Storage
Snapshot of 2026-07-30 · 124 projects
124 storage projects are in the interconnection queue with a Michigan location, totalling 9,297 MW across the 124 that publish a capacity.
Get told what moves in storage in Michigan
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in storage in Michigan: what entered, what moved study phase, what came off the list.
Email me storage in Michigan queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| MISO | 124 | 9,297 MW |
| Status | Projects |
|---|---|
| Active | 63 |
| Withdrawn | 49 |
| Pending Revision Approval | 8 |
| Done | 3 |
| Pending Transfer | 1 |
| County | Projects | Capacity |
|---|---|---|
| Huron | 8 | 950 MW |
| Washtenaw | 7 | 500 MW |
| Saginaw | 5 | 800 MW |
| Ottawa | 5 | 210 MW |
| St. Clair | 5 | 360 MW |
| Branch | 5 | 100 MW |
| Wayne | 5 | 950 MW |
| Van Buren | 4 | 650 MW |
| Gratiot | 4 | 200 MW |
| Kent | 4 | 200 MW |
| Monroe | 4 | 200 MW |
| Genesee | 4 | 450 MW |
| Lenawee | 4 | 210 MW |
| Allegan | 4 | 400 MW |
| Macomb | 3 | 252 MW |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| MISO | 2026-07-30 | 2026-07-30 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.