Interconnection queue › Arkansas › Hybrid
Snapshot of 2026-07-30 · 67 projects
67 hybrid projects are in the interconnection queue with a Arkansas location, totalling 5,922 MW across the 67 that publish a capacity.
Get told what moves in hybrid in Arkansas
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in hybrid in Arkansas: what entered, what moved study phase, what came off the list.
Email me hybrid in Arkansas queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| MISO | 65 | 5,652 MW |
| SPP | 2 | 270 MW |
| Status | Projects |
|---|---|
| Withdrawn | 39 |
| Active | 20 |
| Done | 5 |
| Pending Revision Approval | 1 |
| ERAS | 1 |
| None | 1 |
| County | Projects | Capacity |
|---|---|---|
| Craighead | 6 | 250 MW |
| Mississippi | 6 | 1,655 MW |
| Cross | 4 | 0 MW |
| Lonoke | 4 | 120 MW |
| Poinsett | 4 | 100 MW |
| Crittenden | 4 | 550 MW |
| Phillips | 3 | 200 MW |
| Jefferson | 3 | 600 MW |
| Lee | 3 | 340 MW |
| Pulaski | 2 | 0 MW |
| White | 2 | 100 MW |
| Grant | 2 | 500 MW |
| Ouachita | 2 | 130 MW |
| Arkansas | 2 | 200 MW |
| St. Francis | 2 | 80 MW |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| MISO | 2026-07-30 | 2026-07-30 | source file |
| SPP | 2026-07-30 | 2026-07-30 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.