Interconnection queue › Iowa › Gas
Snapshot of 2026-07-30 · 16 projects
16 gas projects are in the interconnection queue with a Iowa location, totalling 2,357 MW across the 16 that publish a capacity.
Get told what moves in gas in Iowa
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in gas in Iowa: what entered, what moved study phase, what came off the list.
Email me gas in Iowa queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| MISO | 12 | 2,313 MW |
| SPP | 4 | 44 MW |
| Status | Projects |
|---|---|
| Active | 9 |
| None | 3 |
| Withdrawn | 2 |
| Done | 1 |
| IA FULLY EXECUTED/COMMERCIAL OPERATION | 1 |
| County | Projects | Capacity |
|---|---|---|
| Washington | 2 | 875 MW |
| Cerro Gordo | 2 | 525 MW |
| Adair | 2 | 263 MW |
| Sioux Center | 2 | 12 MW |
| Audubon County | 1 | 0 MW |
| Linn County | 1 | 95 MW |
| Dubuque | 1 | 160 MW |
| Clinton | 1 | 160 MW |
| Franklin | 1 | 160 MW |
| Marshall | 1 | 75 MW |
| Sioux | 1 | 15 MW |
| Hardin | 1 | 17 MW |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| MISO | 2026-07-30 | 2026-07-30 | source file |
| SPP | 2026-07-30 | 2026-07-30 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.