Interconnection queueMissouri › Storage

Storage Projects in the Missouri Interconnection Queue

Snapshot of 2026-07-30 · 25 projects

25 storage projects are in the interconnection queue with a Missouri location, totalling 2,943 MW across the 25 that publish a capacity.

Grouped from the ISOs' own fuel codes — see the mapping. Codes we could not match to a published definition are left unclassified rather than assigned here.

Get told what moves in storage in Missouri

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in storage in Missouri: what entered, what moved study phase, what came off the list.

Email me storage in Missouri queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
MISO181,515 MW
SPP71,428 MW

By status, as published

StatusProjects
Withdrawn12
DISIS STAGE7
Active5
Pending Revision Approval1

Top counties

CountyProjectsCapacity
Callaway265 MW
Clay2350 MW
Jackson2399 MW
Scott10 MW
St. Francois10 MW
Bollinger1150 MW
Boone10 MW
Montgomery10 MW
Clark10 MW
Warren County150 MW
Stoddard County150 MW
Jefferson1250 MW
St. Charles1100 MW
New Madrid10 MW
Gasconade1300 MW

Where each number came from

ISOWe last readSource last changedSource
MISO2026-07-302026-07-30 (changed this snapshot)source file
SPP2026-07-302026-07-30 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.