Snapshot of 2026-07-30 · 190 projects · MISO, SPP
There are 190 projects in the interconnection queue with a Missouri location, totalling 25,544 MW across the 190 that publish a capacity.
Get told what moves in Missouri
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Missouri: what entered, what moved study phase, what came off the list.
Email me Missouri queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| MISO | 129 | 14,640 MW |
| SPP | 61 | 10,904 MW |
Shown in each ISO's own coding — a state served by more than one ISO will show more than one spelling of the same technology, and we do not silently merge them here.
| Fuel | Projects | Capacity |
|---|---|---|
| Solar | 69 | 6,250 MW |
| (not published) | 36 | 6,196 MW |
| Battery Storage | 18 | 1,515 MW |
| Wind | 17 | 1,050 MW |
| Hybrid | 16 | 2,065 MW |
| Gas | 7 | 3,513 MW |
| Battery | 7 | 1,428 MW |
| CT | 6 | 256 MW |
| Solar/Storage | 4 | 525 MW |
| Coal | 4 | 1,240 MW |
| Combustion Turbine | 3 | 1,151 MW |
| Photovoltaic | 2 | 295 MW |
| Hydro | 1 | 60 MW |
| County | Projects | Capacity |
|---|---|---|
| Callaway | 8 | 1,115 MW |
| Jackson | 6 | 849 MW |
| Stoddard | 5 | 200 MW |
| Bollinger | 5 | 800 MW |
| Audrain County | 5 | 0 MW |
| Clay | 5 | 850 MW |
| Macon | 4 | 508 MW |
| Randolph | 4 | 115 MW |
| Montgomery | 4 | 100 MW |
| Scott County | 4 | 349 MW |
| Joplin | 4 | 334 MW |
| Scott | 3 | 256 MW |
| Pemiscot | 3 | 0 MW |
| Stoddard County | 3 | 275 MW |
| Warren County | 3 | 489 MW |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| MISO | 2026-07-30 | 2026-07-30 | source file |
| SPP | 2026-07-30 | 2026-07-30 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.