Interconnection queue › New York › Nassau County
Snapshot of 2026-08-06 · 47 projects · New York (NY)
There are 47 projects in the interconnection queue located in Nassau County, New York (NY), totalling 25,924 MW across the 46 that publish a capacity.
Get told what moves in Nassau County, New York
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Nassau County, New York: what entered, what moved study phase, what came off the list.
Email me Nassau County, New York queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| NYISO | 47 | 25,924 MW |
Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here — the national table is the only place any fuel code is mapped.
| Fuel | Projects | Capacity |
|---|---|---|
| ES | 20 | 2,736 MW |
| W | 20 | 20,818 MW |
| CT | 3 | 618 MW |
| ST | 1 | 37 MW |
| AC | 1 | not published |
| DC | 1 | 275 MW |
| CW | 1 | 1,440 MW |
| Status | Projects | Capacity |
|---|---|---|
| Withdrawn | 47 | 25,924 MW |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| OW Ocean Winds East 3 | NYISO | 1,600 | Withdrawn | 2021-05-27 | not published |
| EI Empire ESS II | NYISO | 1,440 | Withdrawn | 2021-05-21 | not published |
| Vineyard Wind I | NYISO | 1,403 | Withdrawn | 2020-04-30 | not published |
| Bluepoint Wind 4 | NYISO | 1,382 | Withdrawn | 2023-09-26 | not published |
| Vineyard Mid-Atlantic 2 | NYISO | 1,330 | Withdrawn | 2022-09-28 | not published |
| Vineyard Mid-Atlantic 3 | NYISO | 1,330 | Withdrawn | 2022-11-30 | not published |
| NY Wind - New Bridge Road | NYISO | 1,325 | Withdrawn | 2020-07-27 | not published |
| Community OSW Barrett 3 | NYISO | 1,310 | Withdrawn | 2023-12-21 | not published |
| EI Glenwood Landing | NYISO | 1,300 | Withdrawn | 2020-05-27 | not published |
| NY Wind - Shore Road | NYISO | 1,272 | Withdrawn | 2020-07-27 | not published |
| EI Oceanside 2 | NYISO | 1,260 | Withdrawn | 2019-12-11 | not published |
| OW Ocean Winds East 1 | NYISO | 1,200 | Withdrawn | 2021-05-18 | not published |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| NYISO | 2026-08-06 | 2026-07-16 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.