Interconnection queue › NYISO

NYISO (New York ISO) Interconnection Queue

NYISO (New York ISO) (NYISO) snapshot of 2026-08-18 · 1,638 projects

The NYISO (New York ISO) (NYISO) queue currently lists 1,638 projects, totalling 344,904 MW across the 1,481 of them that publish a capacity.

By fuel, as published

Reproduced using NYISO's own codes. The national table maps these onto shared buckets; this one does not.

FuelProjectsCapacity
ES51366,566 MW (from 509 of 513 projects)
S37023,841 MW (from 365 of 370 projects)
W255114,226 MW (from 254 of 255 projects)
(not published)11828,524 MW (from 80 of 118 projects)
AC1115,548 MW (from 11 of 111 projects)
CR737,438 MW (from 71 of 73 projects)
DC5250,040 MW (from 48 of 52 projects)
CC3318,588 MW
CT316,979 MW
M1351 MW
H122,752 MW
ST111,778 MW
FC8137 MW
PS75,600 MW
NG6534 MW (from 4 of 6 projects)
C42,153 MW
D41,344 MW
Solar480 MW
Wo363 MW
CW34,240 MW
NU21,752 MW
OSW22,631 MW
F120 MW
SW119 MW
O1not published

By status, as published

NYISO uses its own status vocabulary. We reproduce it exactly — mapping it onto a shared 'active / withdrawn' scale would be us asserting something the ISO did not.

StatusProjectsCapacity
Withdrawn1,452319,095 MW (from 1,307 of 1,452 projects)
Active9610,328 MW (from 87 of 96 projects)
Cluster Study9015,481 MW (from 87 of 90 projects)

Get told what moves in NYISO

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in NYISO: what entered, what moved study phase, what came off the list.

Email me NYISO queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

Top states

StateProjectsCapacity
New York1,600335,608 MW (from 1,444 of 1,600 projects)
Pennsylvania287,664 MW (from 27 of 28 projects)
New Jersey81,593 MW
Connecticut120 MW
Delaware120 MW

Top counties

CountyProjectsCapacity
Suffolk14730,479 MW (from 144 of 147 projects)
(not published)8131,369 MW (from 80 of 81 projects)
Queens6316,362 MW (from 59 of 63 projects)
Orange503,882 MW
Nassau4725,924 MW (from 46 of 47 projects)
Kings4323,495 MW (from 40 of 43 projects)
Jefferson363,652 MW
Chautauqua344,480 MW (from 33 of 34 projects)
NY2913,700 MW (from 28 of 29 projects)
St. Lawrence293,939 MW
Montgomery284,085 MW (from 27 of 28 projects)
Clinton284,787 MW (from 26 of 28 projects)
Niagara275,003 MW (from 24 of 27 projects)
Madison271,164 MW
Herkimer272,389 MW

Where each number came from

Read this before quoting a figure. We re-read every source every week, but a weekly read of an unchanged file is not weekly data. These have not moved in a while: NYISO last changed 2026-08-13 (6 identical reads since). Those rows are exactly as current as the ISO's own published file, and no more.
ISOWe last readSource last changedSource
NYISO2026-08-182026-08-13 (unchanged across 6 weekly reads)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.