Interconnection queueTexas › Wind

Wind Projects in the Texas Interconnection Queue

Snapshot of 2026-07-30 · 170 projects

170 wind projects are in the interconnection queue with a Texas location, totalling 49,480 MW across the 170 that publish a capacity.

Grouped from the ISOs' own fuel codes — see the mapping. Codes we could not match to a published definition are left unclassified rather than assigned here.

Get told what moves in wind in Texas

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in wind in Texas: what entered, what moved study phase, what came off the list.

Email me wind in Texas queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
ERCOT15847,360 MW
MISO6219 MW
SPP61,900 MW

By status, as published

StatusProjects
SS Completed, FIS Started, No IA71
SS Completed, FIS Completed, IA49
SS Completed, FIS Started, IA29
Withdrawn5
DISIS STAGE5
SS Completed, FIS Completed, No IA4
SS Started, FIS Started, No IA4
Active1
SS Completed, FIS Not Started, IA1
ERAS1

Top counties

CountyProjectsCapacity
Nolan111,270 MW
Pecos113,642 MW
Zapata91,974 MW
Glasscock7981 MW
Jim Hogg51,746 MW
Starr4999 MW
Webb41,296 MW
Upton41,240 MW
Taylor3256 MW
Sterling3575 MW
Eastland312 MW
Willacy3686 MW
Fisher31,144 MW
Howard3254 MW
Navarro3734 MW

Where each number came from

Read this before quoting a figure. We re-read every source every week, but a weekly read of an unchanged file is not weekly data. These have not moved in a while: ERCOT last changed 2026-06-11 (9 identical reads since). Those rows are exactly as current as the ISO's own published file, and no more.
ISOWe last readSource last changedSource
ERCOT2026-07-302026-06-11 (unchanged across 9 weekly reads)source file
MISO2026-07-302026-07-30 (changed this snapshot)source file
SPP2026-07-302026-07-30 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.