Interconnection queue changes in Michigan

This page is not part of the subscription. Over 56 days of collection this queue produced 71 named movers. We keep the dated copies and this page stays here, but we are not selling it, and the weekly file does not include it. The table below is every move we hold for Michigan: 106 of them across 10 dated copies going back to 11 Jun 2026, and every row names the two dates it sits between.

Price
$49/mo
Built for
Energy researchers, journalists, interconnection-software vendors
Read
About every week
Newest sealed read
2026-08-06

Subscribe — $49 a month$49 a month, billed monthly, for dated what-moved files of the California ISO interconnection queue only. Not the Southwest Power Pool, not ISO New England, not the New York ISO, and not a four-queue blend. One file a week, built from daily seals. A week with no tracked-field moves is still sent: added 0, removed 0, changed 0, plus the two content hashes of the workbooks compared. This file uses material published by the California ISO. Copyright © 2026 California Independent System Operator. All rights reserved. Their terms say "Most of the materials", not all. This file does not claim the Public Queue Report is inside that "Most". Cancel any month by email, with no account to close and no notice period.

Newest sealed read: 2026-08-06. We read this source about every 7 days. We hold 10 sealed runs going back to 2026-06-11. Collection has paused. We last read this source 24 days ago, and we read it about every 7 days, so no number on this page moves until collection starts again.

What this page is5,108 rows held · newest sealed read 2026-08-06

  • This page is not part of the subscription. Over 56 days of collection this queue produced 71 named movers. We keep the dated copies and this page stays here, but we are not selling it, and the weekly file does not include it.
  • 530 power projects in Michigan sit in the newest copy we hold of this waiting list: MISO.
  • We hold 10 dated copies covering Michigan, the first from 11 Jun 2026 and the most recent read on 6 Aug 2026, and 5,108 dated project rows inside them.
  • Nothing in Michigan changed between our newest copy and the newest copy at least a week older than it (30 Jul 2026 → 6 Aug 2026). The table above is the most recent set of moves we do hold, and every row names the two dates it sits between.
  • The biggest single project in Michigan in the newest copy is BLACKFOOT - MADRID 345.0kV at 1,452 MW.

Real rows out of our sealed copies

These are rows we read out of dated copies we keep ourselves. The live source shows today only, so once a row moves, what it said before is gone from the place you would go to look.

12 of 106 moves we hold for Michigan, newest first — the rest are in the dated copies we keep. None of this page is in the weekly file 23 Jul 2026 → 30 Jul 2026
ProjectWhereSizeWhat moved
MAJESTIC - ONEIDA 345.0kVCalhoun255 MWstatus Pending Revision Approval → Active
ARGENTA - MORROW 138.0kVKalamazoo220 MWstatus Pending Revision Approval → Active
ARGENTA - TWIN BRANCH 345.0kVVan Buren220 MWstatus Pending Revision Approval → Active
IOSCO - SPRUCE ROAD 138.0kVAlcona215 MWstatus Pending Revision Approval → Active
ARGENTA - PALISADES 345.0kVVan Buren200 MWstatus Pending Revision Approval → Active
Toll Rd 120kVMonroe200 MWstatus Pending Revision Approval → Active
BLACKFOOT - MADRID 345.0kVLivingston180 MWstatus Pending Revision Approval → Active
COLFAX - MADRID 120.0kVLivingston160 MWstatus Pending Revision Approval → Active
Hagensville 138 kV SubstationPresque Isle150 MWstatus Pending Revision Approval → Active
Eureka - Vestaburg 138kVMontcalm150 MWstatus Pending Revision Approval → Active
MOORE ROADHillsdale140 MWstatus Pending Revision Approval → Active
MURPHY - TITTABAWASSEE 345.0kVMidland129 MWstatus Pending Revision Approval → Active
The 12 biggest projects in Michigan, out of 530 — whatever status the file gives them read 6 Aug 2026
ProjectWhereWhat it isSizeStatus
BLACKFOOT - MADRID 345.0kVLivingstonGas1,452 MWPending Revision Approval
HIPLEBranchGas1,445 MWPending Revision Approval
Majestic-Milan 345 kV LineWashtenawGas1,414 MWActive
Belle River - Fitz #2 345 kV Line TapSt. Clair CountyGas1,209 MWDone
THETFORDGeneseeGas975.4 MWActive
Orr RD 138 kV SubstationSaginaw CountyGas725 MWWithdrawn
Argenta - Tompkins 345kV Line TapCalhoun CountyGas535 MWWithdrawn
Stein - Rapson 345 kV lineHuronBattery500 MWActive
Argenta to Tompkins 345kV lineCalhounMore than one kind499 MWDone
Vergennes - Nelson Rd 345 kV Line TapMontcalm CountyWind374.4 MWWithdrawn
RIVER ROUGEWayneBattery350 MWActive
BATTLE CREEK - ONEIDA 345.0kVCalhounSolar309 MWActive

Who published the data on this page

  • Every row on this page was published by a grid operator, not by us. Written out in full, they are Midcontinent Independent System Operator. We keep dated copies of their public queue files; the projects, the names and the wording inside those rows are theirs.
  • This file uses material published by the California ISO.
  • Copyright © 2026 California Independent System Operator. All rights reserved.
  • Their terms say "Most of the materials", not all. This file does not claim the Public Queue Report is inside that "Most".

What this page cannot tell you

  • This is our last copy of the MISO file. We sealed it on 6 Aug 2026 and we have not asked for it since, so every row and every date here stays exactly where it is. We are not promising you another one. Nothing is trying to fetch it, so nothing here is going to move on its own. If we start reading it again the date at the top changes and you will see it.
  • The operators write the same fuel differently — Solar, SOL, SUN and S all appear for the same thing. The fuel column is our reading of their labels, not their own count, and a label we are not sure of is shown as not clear rather than guessed at.
  • MISO has written this state as "Michigan" in some dated copies and as "MI" in others, for the same projects. We count both, so the project total does not jump about when the operator changes how it spells a state.
  • A move here means two dated copies of the same public file disagree. It is not a decision, an approval, or a filing. If you need to know why a project moved, the operator is the place to ask, not us. Email operations@ustechautomations.com and we will send you both dated copies so you can check ours.

See the file before you pay

You do not have to take our word for what is in the file. Here are 17 rows of the real thing, carrying all 9 of its columns, cut out of the dated copies we sealed ourselves. Nothing in it is made up and nothing in it is tidied up.

  • Open the 17 rows as a CSVA plain spreadsheet file. It saves to your machine rather than painting itself into a browser tab, and it opens in Excel, Numbers or Google Sheets.
  • The same 17 rows as JSONThe same rows again, laid out for reading with code.

What arrives after you pay: a person emails you the whole file as a CSV — the same plain spreadsheet as the sample file above, not a login and not a web page — within one working day of your payment.

What you would be paying for: $49 a month, billed monthly, for dated what-moved files of the California ISO interconnection queue only. Not the Southwest Power Pool, not ISO New England, not the New York ISO, and not a four-queue blend. One file a week, built from daily seals. A week with no tracked-field moves is still sent: added 0, removed 0, changed 0, plus the two content hashes of the workbooks compared. This file uses material published by the California ISO. Copyright © 2026 California Independent System Operator. All rights reserved. Their terms say "Most of the materials", not all. This file does not claim the Public Queue Report is inside that "Most". Cancel any month by email, with no account to close and no notice period. After you pay, a person emails you the first California ISO what-moved file as a CSV within one working day, then a new one every week for as long as the subscription runs. Each file names the two sealed dates compared. If we could not collect that week, the file says so rather than repeating itself.

These 17 rows are a slice of the file, not the whole of it. What we cannot show you here is how far back it goes: that is the part you are paying for.

Subscribe to this feed

$49/mo · a closed set of dated copies to 6 Aug 2026, not being added to

Subscribe — $49 a month

$49 a month, billed monthly, for dated what-moved files of the California ISO interconnection queue only. Not the Southwest Power Pool, not ISO New England, not the New York ISO, and not a four-queue blend. One file a week, built from daily seals. A week with no tracked-field moves is still sent: added 0, removed 0, changed 0, plus the two content hashes of the workbooks compared. This file uses material published by the California ISO. Copyright © 2026 California Independent System Operator. All rights reserved. Their terms say "Most of the materials", not all. This file does not claim the Public Queue Report is inside that "Most". Cancel any month by email, with no account to close and no notice period. After you pay, a person emails you the first California ISO what-moved file as a CSV within one working day, then a new one every week for as long as the subscription runs. Each file names the two sealed dates compared. If we could not collect that week, the file says so rather than repeating itself.

Rather ask first? Email operations@ustechautomations.com. Say that you want Michigan and we will tell you which weeks we hold for it before you pay.