Newest sealed read: 2026-08-06. We read this source about every 7 days. We hold 10 sealed runs going back to 2026-06-11. Collection has paused. We last read this source 41 days ago, and we read it about every 7 days, so no number on this page moves until collection starts again.
What this page is2,770 rows held · newest sealed read 2026-08-06
- This page is not part of the subscription. Over 56 days of collection this queue produced 15 named movers. We keep the dated copies and this page stays here, but we are not selling it, and the weekly file does not include it.
- 284 power projects in Minnesota sit in the newest copy we hold of this waiting list: MISO.
- We hold 10 dated copies covering Minnesota, the first from 11 Jun 2026 and the most recent read on 6 Aug 2026, and 2,770 dated project rows inside them.
- 4 projects in Minnesota moved between our newest copy and the newest copy at least a week older than it (30 Jul 2026 → 6 Aug 2026).
- The biggest single project in Minnesota in the newest copy is Lyon County - Cedar Mountain 345 kV Line Tap at 600 MW.
Real rows out of our sealed copies
These are rows we read out of dated copies we keep ourselves. The live source shows today only, so once a row moves, what it said before is gone from the place you would go to look.
| Project | Where | Size | What moved | Between |
|---|---|---|---|---|
| North Rochester - Briggs Road 345.0kV | Wabasha | 200 MW | status Pending Revision Approval → Active | 30 Jul 2026 → 6 Aug 2026 |
| Jackson North 161kV Substation | Jackson | 150 MW | status Pending Revision Approval → Active | 30 Jul 2026 → 6 Aug 2026 |
| Plummer Pipe | Red Lake | 130 MW | status Pending Revision Approval → Active | 30 Jul 2026 → 6 Aug 2026 |
| SHERBURNE CO | Meeker | 0 MW | status Withdrawn → Active | 30 Jul 2026 → 6 Aug 2026 |
| Lake Yankton to Lyon County 115kV | Lyon | 235 MW | status Pending Revision Approval → Active | 23 Jul 2026 → 30 Jul 2026 |
| Hancock 115kV Substation | Stevens | 160 MW | status Pending Revision Approval → Active | 23 Jul 2026 → 30 Jul 2026 |
| Rush City 230 kV | Chisago | 150 MW | status Pending Revision Approval → Active | 16 Jul 2026 → 23 Jul 2026 |
| MORRISON DITCH | Benton | 0 MW | new in this file | 9 Jul 2026 → 16 Jul 2026 |
| Riel (MH) - Roseau County North 500.0kV | Roseau | 500 MW | status Pending Revision Approval → Active | 2 Jul 2026 → 9 Jul 2026 |
| Lake Yankton to Lyon County 115kV | Lyon | 235 MW | status Active → Pending Revision Approval | 2 Jul 2026 → 9 Jul 2026 |
| LYON COUNTY | Lyon | 200 MW | status Pending Revision Approval → Active | 2 Jul 2026 → 9 Jul 2026 |
| North Rochester - Briggs Road 345.0kV | Wabasha | 200 MW | status Active → Pending Revision Approval | 2 Jul 2026 → 9 Jul 2026 |
| Project | Where | What it is | Size | Status |
|---|---|---|---|---|
| Lyon County - Cedar Mountain 345 kV Line Tap | Cottonwood County,Murray County,Redwood County | Wind | 600 MW | Withdrawn |
| Riel (MH) - Roseau County North 500.0kV | Roseau | Solar | 500 MW | Active |
| ALEXANDRIA - BISON 345.0kV | Clay | Solar | 430 MW | Active |
| Lyon County - Cedar Mountain 345 kV Circuit 2 Line | Redwood County | Wind | 414 MW | Withdrawn |
| Crandall 345 kV Substation | Cottonwood County | More than one kind | 335 MW | Withdrawn |
| NROC 3 (601039) to PR ISLD3 (601003) 345 kV line | Goodhue | Battery | 330 MW | Active |
| HAMPTON 345 KV | Dakota | Battery | 300 MW | Active |
| Big Stone South - Alexandria 345kV | Big Stone | Wind | 300 MW | Active |
| Hampton - Prairie Island 345.0kV | Goodhue | Solar | 300 MW | Active |
| Big Stone South - Alexandira 345kV | Big Stone | Wind | 300 MW | Active |
| Big Stone South - Deuel County 345.0kV | Lac qui Parle | Wind | 300 MW | Active |
| Arrowhead - Bear Creek (GRE) 230kV | Pine | More than one kind | 288 MW | Active |
Who published the data on this page
- Every row on this page was published by a grid operator, not by us. Written out in full, they are Midcontinent Independent System Operator. We keep dated copies of their public queue files; the projects, the names and the wording inside those rows are theirs.
- This file uses material published by the California ISO.
- Copyright © 2026 California Independent System Operator. All rights reserved.
- Their terms say "Most of the materials", not all. This file does not claim the Public Queue Report is inside that "Most".
What this page cannot tell you
- This is our last copy of the MISO file. We sealed it on 6 Aug 2026 and we have not asked for it since, so every row and every date here stays exactly where it is. We are not promising you another one. Nothing is trying to fetch it, so nothing here is going to move on its own. If we start reading it again the date at the top changes and you will see it.
- The operators write the same fuel differently — Solar, SOL, SUN and S all appear for the same thing. The fuel column is our reading of their labels, not their own count, and a label we are not sure of is shown as not clear rather than guessed at.
- A move here means two dated copies of the same public file disagree. It is not a decision, an approval, or a filing. If you need to know why a project moved, the operator is the place to ask, not us. Email operations@ustechautomations.com and we will send you both dated copies so you can check ours.
See the file before you pay
You do not have to take our word for what is in the file. Here are 25 rows of the real thing, carrying all 9 of its columns, cut out of the dated copies we sealed ourselves. Nothing in it is made up and nothing in it is tidied up.
- Open the 25 rows as a CSVA plain spreadsheet file. It saves to your machine rather than painting itself into a browser tab, and it opens in Excel, Numbers or Google Sheets.
- The same 25 rows as JSONThe same rows again, laid out for reading with code.
What arrives after you pay: Stripe sends you to the receipt page. After payment confirmation, your dated California ISO CSV appears there. It compares successfully collected source copies and names any gaps. A failed source read creates no new dated file. Nobody emails you. The subscriber CSV adds source and coverage columns to the compact preview shown here. A coverage row records the comparison dates and any gaps, including when no changes were observed.
What you would be paying for: $49 a month, billed monthly, for dated what-moved files of the California ISO interconnection queue only. A dated file is built from successful CAISO seals when available. When the two comparison copies have no tracked-field moves, it records added 0, removed 0, changed 0, plus the two content hashes of the workbooks compared; a failed or missing source read creates no new dated file and remains an explicit gap. This file uses material published by the California ISO. Copyright © 2026 California Independent System Operator. All rights reserved. Their terms say "Most of the materials", not all. This file does not claim the Public Queue Report is inside that "Most". Cancel any month by email, with no account to close and no notice period. After payment confirmation, your dated California ISO file appears on the receipt page. A dated CSV appears only after successfully collected source copies; each file names the two sealed dates compared and its source hashes. If an intervening source read fails, the gap is reported and no new dated file is created from that failure.
These 25 rows are a slice of the file, not the whole of it. What we cannot show you here is how far back it goes: that is the part you are paying for.
Subscribe to this feed
$49/mo · a closed set of dated copies to 6 Aug 2026, not being added to
Subscribe — $49 a month$49 a month, billed monthly, for dated what-moved files of the California ISO interconnection queue only. A dated file is built from successful CAISO seals when available. When the two comparison copies have no tracked-field moves, it records added 0, removed 0, changed 0, plus the two content hashes of the workbooks compared; a failed or missing source read creates no new dated file and remains an explicit gap. This file uses material published by the California ISO. Copyright © 2026 California Independent System Operator. All rights reserved. Their terms say "Most of the materials", not all. This file does not claim the Public Queue Report is inside that "Most". Cancel any month by email, with no account to close and no notice period. After payment confirmation, your dated California ISO file appears on the receipt page. A dated CSV appears only after successfully collected source copies; each file names the two sealed dates compared and its source hashes. If an intervening source read fails, the gap is reported and no new dated file is created from that failure.
Rather ask first? Email operations@ustechautomations.com. Say that you want Minnesota and we will tell you which weeks we hold for it before you pay.