Newest sealed read: 2026-07-30. We read this source about every 7 days. We hold 10 sealed runs going back to 2026-06-11. Collection has paused. We last read this source 77 days ago, and we read it about every 7 days, so no number on this page moves until collection starts again.
What this page is17,445 rows held · newest sealed read 2026-07-30
- This page is not part of the subscription. Over 56 days of collection this queue produced 4 named movers. We keep the dated copies and this page stays here, but we are not selling it, and the weekly file does not include it.
- 1,930 power projects in Texas sit in the newest copy we hold of each of these waiting lists: ERCOT, MISO. We hold 10 dated copies covering Texas, the first from 11 Jun 2026 and the most recent read on 6 Aug 2026, and 17,445 dated project rows inside them. The picture on this page is complete only as of 30 Jul 2026. ERCOT has 1,839 of the 1,930 projects in Texas — 95% of them — and we have not been able to read that list since then. The rest of the page is current to 6 Aug 2026.
- Each operator here has its own newest copy: ERCOT 30 Jul 2026 (1,839 projects); MISO 6 Aug 2026 (91 projects).
- Nothing in Texas changed between our newest copy and the newest copy at least a week older than it (ERCOT 23 Jul 2026 → 30 Jul 2026; MISO 30 Jul 2026 → 6 Aug 2026). The table above is the most recent set of moves we do hold, and every row names the two dates it sits between.
- The ERCOT file that carries the projects was identical on all 9 of our reads — the same file, down to the byte — so there was nothing in it to move.
- The biggest single project in Texas in the newest copy is Prairie Ridge (Gas - CC) at 1,660.4 MW.
Real rows out of our sealed copies
These are rows we read out of dated copies we keep ourselves. The live source shows today only, so once a row moves, what it said before is gone from the place you would go to look.
| Project | Where | Size | What moved | Between |
|---|---|---|---|---|
| Cypress 138 kV Substation | Hardin | 200 MW | status Pending Revision Approval → Active | 23 Jul 2026 → 30 Jul 2026 |
| ONALASKA | Trinity | 150 MW | status Active → Pending Revision Approval | 9 Jul 2026 → 16 Jul 2026 |
| Rhodair | Jefferson | 0 MW | status Active → Withdrawn | 9 Jul 2026 → 16 Jul 2026 |
| Cypress 138 kV Substation | Hardin | 200 MW | status Active → Pending Revision Approval | 26 Jun 2026 → 2 Jul 2026 |
| 138kV Bragg - SHECO Menard Line | Polk | 170 MW | status Pending Revision Approval → Active | 26 Jun 2026 → 2 Jul 2026 |
| 138kV Bragg - SHECO Menard Line | Polk | 170 MW | status Active → Pending Revision Approval | 18 Jun 2026 → 25 Jun 2026 |
| Project | Operator | Where | What it is | Size | Status |
|---|---|---|---|---|---|
| Prairie Ridge (Gas - CC) | ERCOT | Franklin | Gas | 1,660.4 MW | SS Completed, FIS Started, No IA |
| Hecate Energy Orem Wind | ERCOT | Brazoria | Wind | 1,542 MW | SS Completed, FIS Started, No IA |
| Aegle Power | ERCOT | Cameron | Gas | 1,536.4 MW | SS Completed, FIS Started, No IA |
| Big Canyon Wind | ERCOT | Pecos | Wind | 1,500 MW | SS Completed, FIS Started, IA |
| Caldwell County Energy Center | ERCOT | Caldwell | Gas | 1,500 MW | SS Completed, FIS Started, No IA |
| BasRanch (TEF - Due Diligence) | ERCOT | Ward | Gas | 1,350 MW | SS Completed, FIS Completed, IA |
| STP Unit2 High Pressure Turbine Upgrade | ERCOT | Matagorda | Nuclear | 1,336.5 MW | SS Started, FIS Started, No IA |
| Moon Hammer | ERCOT | Wheeler | Gas | 1,300 MW | SS Completed, FIS Started, IA |
| The Giant Arc-II | ERCOT | Pecos | Gas | 1,300 MW | SS Started, FIS Started, No IA |
| The Giant Arc I | ERCOT | Pecos | Gas | 1,300 MW | SS Started, FIS Started, No IA |
| Sandow Lakes Energy Station | ERCOT | Milam | Gas | 1,291.6 MW | SS Completed, FIS Started, No IA |
| Jewett Energy Center 1 Gas | ERCOT | Freestone | Gas | 1,274 MW | SS Completed, FIS Started, No IA |
Who published the data on this page
- Every row on this page was published by a grid operator, not by us. Written out in full, they are Midcontinent Independent System Operator and Electric Reliability Council of Texas. We keep dated copies of their public queue files; the projects, the names and the wording inside those rows are theirs.
- This file uses material published by the California ISO.
- Copyright © 2026 California Independent System Operator. All rights reserved.
- Their terms say "Most of the materials", not all. This file does not claim the Public Queue Report is inside that "Most".
What this page cannot tell you
- This is our last copy of the ERCOT file. We sealed it on 30 Jul 2026 and we have not asked for it since, so every row and every date here stays exactly where it is. We are not promising you another one. Nothing is trying to fetch it, so nothing here is going to move on its own. If we start reading it again the date at the top changes and you will see it.
- This is our last copy of the MISO file. We sealed it on 6 Aug 2026 and we have not asked for it since, so every row and every date here stays exactly where it is. We are not promising you another one. Nothing is trying to fetch it, so nothing here is going to move on its own. If we start reading it again the date at the top changes and you will see it.
- The operators write the same fuel differently — Solar, SOL, SUN and S all appear for the same thing. The fuel column is our reading of their labels, not their own count, and a label we are not sure of is shown as not clear rather than guessed at.
- A move here means two dated copies of the same public file disagree. It is not a decision, an approval, or a filing. If you need to know why a project moved, the operator is the place to ask, not us. Email operations@ustechautomations.com and we will send you both dated copies so you can check ours.
See the file before you pay
You do not have to take our word for what is in the file. Here are 25 rows of the real thing, carrying all 9 of its columns, cut out of the dated copies we sealed ourselves. Nothing in it is made up and nothing in it is tidied up.
- Open the 25 rows as a CSVA plain spreadsheet file. It saves to your machine rather than painting itself into a browser tab, and it opens in Excel, Numbers or Google Sheets.
- The same 25 rows as JSONThe same rows again, laid out for reading with code.
What arrives after you pay: Stripe sends you to the receipt page. A job that checks for new payments every 10 minutes puts the newest weekly California ISO CSV there and adds each later week's file while your subscription is active; if no weekly file has been built yet, the page says so. It compares successfully collected source copies and names any gaps. A failed source read creates no new dated file. Nobody emails you. The subscriber CSV adds source and coverage columns to the compact preview shown here. A coverage row records the comparison dates and any gaps, including when no changes were observed.
What you would be paying for: $49 a month, billed monthly, for dated what-moved files of the California ISO interconnection queue only. A dated file is built from successful CAISO seals when available. When the two comparison copies have no tracked-field moves, the file holds one coverage row only (the two comparison dates, the row count and content hash of each workbook, and a note on whether every date in between was fetched) and no project rows; a failed or missing source read creates no new dated file and remains an explicit gap. This file uses material published by the California ISO. Copyright © 2026 California Independent System Operator. All rights reserved. Their terms say "Most of the materials", not all. This file does not claim the Public Queue Report is inside that "Most". Cancel any month by email, with no account to close and no notice period. After you pay, Stripe sends you to your receipt page, where a job that checks for new payments every 10 minutes puts the newest weekly file. A dated CSV appears only after successfully collected source copies; each file names the two sealed dates compared and its source hashes. If an intervening source read fails, the gap is reported and no new dated file is created from that failure.
These 25 rows are a slice of the file, not the whole of it. What we cannot show you here is how far back it goes: that is the part you are paying for.
Subscribe to this feed
$49/mo · a closed set of dated copies to 6 Aug 2026, not being added to
Subscribe — $49 a month$49 a month, billed monthly, for dated what-moved files of the California ISO interconnection queue only. A dated file is built from successful CAISO seals when available. When the two comparison copies have no tracked-field moves, the file holds one coverage row only (the two comparison dates, the row count and content hash of each workbook, and a note on whether every date in between was fetched) and no project rows; a failed or missing source read creates no new dated file and remains an explicit gap. This file uses material published by the California ISO. Copyright © 2026 California Independent System Operator. All rights reserved. Their terms say "Most of the materials", not all. This file does not claim the Public Queue Report is inside that "Most". Cancel any month by email, with no account to close and no notice period. After you pay, Stripe sends you to your receipt page, where a job that checks for new payments every 10 minutes puts the newest weekly file. A dated CSV appears only after successfully collected source copies; each file names the two sealed dates compared and its source hashes. If an intervening source read fails, the gap is reported and no new dated file is created from that failure.
Rather ask first? Email operations@ustechautomations.com. Say that you want Texas and we will tell you which weeks we hold for it before you pay.
More from this feed
- Up one level: Queue changesThe whole feed, its price, and how the file arrives.
- What is and is not in this feedEvery source we read for it, how often, and the ones we refuse to collect.