What Has Changed in the SPP Interconnection Queue

2026-06-11 → 2026-08-06 · every difference we have observed, not just this week's

We have recorded 141 changes across 116 projects in the SPP queue since 2026-06-11: 71 new entries, 37 status changes, 28 in-service dates moved (24 of them later), 1 capacity revisions and 4 projects no longer listed.

Counted across 9 comparisons between consecutive sealed snapshots, 10 snapshots from 2026-06-11 to 2026-08-06 (between 1 and 7 days apart). One change is one difference observed for one project between two consecutive snapshots, so a project that moved in three different weeks is counted three times: these 141 changes come from 116 distinct projects.

This is the part that cannot be refetched. Every ISO publishes its current queue for free and then overwrites it — none of them keep an archive. The dates in the left-hand column below exist only because we sealed a copy that week, and after the fact nobody can reconstruct them, including us.
A project that disappears from a report is recorded here as no longer listed, not as withdrawn. ISOs drop rows for several reasons and only some of them mean the project died — we publish the observation, not a cause we cannot see.

When it moved

SnapshotChanges observed
2026-08-0619
2026-07-303
2026-07-233
2026-07-1665
2026-07-092
2026-07-0222
2026-06-261
2026-06-256
2026-06-1820

Get told what moves in SPP

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in SPP: what entered, what moved study phase, what came off the list.

Email me SPP queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

Status changes

ObservedISOProjectCountyWasNow
2026-08-06SPPGEN-2024-SR15YoakumIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-08-06SPPGEN-2024-SR10LancasterIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-08-06SPPGEN-2023-210LincolnIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-08-06SPPGEN-2023-206SebastianIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-08-06SPPGEN-2019-037MercerIA FULLY EXECUTED/ON SCHEDULEIA FULLY EXECUTED/ON SUSPENSION
2026-08-06SPPIFS-2017-001-15Mayes CountyIA FULLY EXECUTED/ON SCHEDULEIA FULLY EXECUTED/COMMERCIAL OPERATION
2026-08-06SPPIFS-2017-001-14Mayes CountyIA FULLY EXECUTED/ON SCHEDULEIA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-30SPPGEN-2022-038HarrisonIA FULLY EXECUTED/ON SCHEDULEIA FULLY EXECUTED/ON SUSPENSION
2026-07-16SPPGEN-2023-170CharitonIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-07-16SPPGEN-2022-136BryanIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-07-16SPPGEN-2022-130SebastianIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-07-16SPPGEN-2022-038HarrisonIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-07-16SPPGEN-2021-025WoodwardIA FULLY EXECUTED/ON SCHEDULEIA FULLY EXECUTED/ON SUSPENSION
2026-07-02SPPGEN-2023-153PerkinsIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-07-02SPPGEN-2021-025WoodwardIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-07-02SPP24-03011LovelandDISIS STAGEIA PENDING
2026-07-02SPP22-07251WellingtonDISIS STAGEIA FULLY EXECUTED/ON SCHEDULE
2026-07-02SPP21-11157Fort CollinsDISIS STAGEIA FULLY EXECUTED/ON SCHEDULE
2026-07-02SPP21-11121MeadFACILITY STUDY STAGEIA FULLY EXECUTED/ON SCHEDULE
2026-07-02SPP21-08242CheyenneIA PENDINGIA FULLY EXECUTED/ON SUSPENSION
2026-06-25SPPGEN-2025-SR3MinneolaIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-25SPPGEN-2024-SR6Johnston CountyIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-25SPPGEN-2023-SR19Jefferson CountyIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-25SPPGEN-2021-108CassIA FULLY EXECUTED/ON SCHEDULEIA FULLY EXECUTED/ON SUSPENSION
2026-06-18SPPGEN-2023-225LancasterIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2023-224LancasterIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2023-223GageIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2023-222GageIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2023-177GarvinIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2023-161BlaineIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2023-102WoodsIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2023-088Okfuskee/OkmulgeeIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2023-079CassIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2023-078CassIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2023-077CassIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2022-147HaleIA PENDINGIA FULLY EXECUTED/ON SCHEDULE
2026-06-18SPPGEN-2021-038TitusIA PENDINGIA FULLY EXECUTED/ON SCHEDULE

In-service dates that moved

The date a project told its ISO it would start commercial operation, against what the same project published at the previous snapshot. A date appearing for the first time is not counted here — there is no earlier plan for it to have moved from.

ObservedISOProjectMWWasNowMoved
2026-08-06SPPGEN-2024-SR153005/1/20266/1/2028762 days later
2026-08-06SPPGEN-2024-SR108012/31/202611/1/2027305 days later
2026-08-06SPPGEN-2023-2101919/1/20269/1/20291,096 days later
2026-08-06SPPGEN-2023-2065012/31/202912/31/2028365 days earlier
2026-08-06SPPIFS-2017-001-181256/6/20265/6/202631 days earlier
2026-08-06SPPIFS-2017-001-15726/22/20268/3/202642 days later
2026-08-06SPPIFS-2017-001-14725/8/20268/2/202686 days later
2026-07-23SPPGEN-2022-0381804/22/20294/2/2030345 days later
2026-07-23SPPGEN-2018-0031506/1/20279/1/2028458 days later
2026-07-02SPPGEN-2023-2232396/1/20306/1/20331,096 days later
2026-07-02SPPGEN-2023-2224786/1/20306/1/20331,096 days later
2026-07-02SPPGEN-2023-1772006/1/20289/1/2029457 days later
2026-07-02SPPGEN-2023-1531208/31/202811/1/2029427 days later
2026-07-02SPPGEN-2023-1024756/30/20293/1/2029121 days earlier
2026-07-02SPPGEN-2023-08811712/31/20289/29/202893 days earlier
2026-07-02SPPGEN-2022-1541007/15/20299/19/202966 days later
2026-07-02SPPGEN-2022-1472034/11/202512/11/2026609 days later
2026-07-02SPPGEN-2021-0382005/31/20285/1/2029335 days later
2026-07-02SPPGEN-2021-02520312/1/20265/3/2029884 days later
2026-07-02SPPIFS-2017-002-431506/1/202611/20/2026172 days later
2026-07-02SPP24-030111301/1/20271/1/2028365 days later
2026-07-02SPP21-1112115012/31/202512/1/20281,066 days later
2026-07-02SPP21-0824235012/31/202512/1/20281,066 days later
2026-06-25SPPGEN-2025-SR31507/21/20283/31/2030618 days later
2026-06-25SPPGEN-2023-SR19509/8/202611/1/2027419 days later
2026-06-18SPPGEN-2023-0782552/1/20289/22/2028234 days later
2026-06-18SPPGEN-2023-0772552/1/20289/22/2028234 days later
2026-06-18SPPIFS-2017-002-7311512/31/20247/1/20281,278 days later

New queue entries

ObservedISOProjectCountyFuelMWStatus
2026-08-06SPPGEN-2026-PR23Earth252SPECIAL STUDY
2026-08-06SPPGEN-2026-PR22Rogers104SPECIAL STUDY
2026-08-06SPPGEN-2026-PR21Earth45SPECIAL STUDY
2026-08-06SPPGEN-2026-PR20Earth30SPECIAL STUDY
2026-08-06SPPGEN-2026-PR19Hobbs14SPECIAL STUDY
2026-07-30SPPGEN-2026-SR30Thomas County504SPECIAL STUDY
2026-07-30SPPGEN-2026-SR29Thomas County197SPECIAL STUDY
2026-07-23SPPGEN-2026-SR28Dodge City298SPECIAL STUDY
2026-07-16SPPGEN-2026-SR27Muskogee300SPECIAL STUDY
2026-07-16SPPGEN-2026-SR26Burlington150SPECIAL STUDY
2026-07-16SPPGEN-2026-SR25Burlington150SPECIAL STUDY
2026-07-16SPPASGI-2024-024Saint Joseph79None
2026-07-16SPPASGI-2024-023HempsteadSolar/Storage120None
2026-07-16SPPASGI-2024-020McPhersonGas124None
2026-07-16SPPASGI-2024-019Sioux CenterGas6None
2026-07-16SPPASGI-2024-018Sioux CenterGas6None
2026-07-16SPPASGI-2024-017Booneville5None
2026-07-16SPPASGI-2024-016Boonville5None
2026-07-16SPPASGI-2024-015Bonanza5None
2026-07-16SPPASGI-2024-014DeQueen5None
2026-07-16SPPASGI-2024-013Nashville10None
2026-07-16SPPASGI-2024-012Big Horn300None
2026-07-16SPPASGI-2024-009Nashville8None
2026-07-16SPPASGI-2024-008ColoumbiaGas86None
2026-07-16SPPASGI-2024-007SalineGas48None
2026-07-16SPPASGI-2024-006TexasSolar/Storage100None
2026-07-16SPPASGI-2024-005Mena5None
2026-07-16SPPASGI-2024-004Redfield8None
2026-07-16SPPASGI-2024-003Morton80None
2026-07-16SPPASGI-2024-002Boise CitySolar/Battery30None
2026-07-16SPPASGI-2024-001HardinNatural Gas17None
2026-07-16SPPASGI-2023-001Eddy20None
2026-07-16SPPASGI-2021-003Solar/Storage40DISIS STAGE
2026-07-16SPPASGI-2021-001Solar/Storage50DISIS STAGE
2026-07-16SPPASGI-2020-003Solar/Storage35DISIS STAGE
2026-07-16SPPASGI-2020-001Solar/Storage35DISIS STAGE
2026-07-16SPPASGI-2019-001Teton20None
2026-07-16SPPASGI-2018-011Franklin35DISIS STAGE
2026-07-16SPPASGI-2018-010Franklin35DISIS STAGE
2026-07-16SPPASGI-2018-007Chariton County20DISIS STAGE
2026-07-16SPPASGI-2018-006Vernon County20DISIS STAGE
2026-07-16SPPASGI-2018-003Appleton City20DISIS STAGE
2026-07-16SPPASGI-2018-001Nodaway230IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2017-006Nodaway238IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2017-001Alta4DISIS STAGE
2026-07-16SPPASGI-2016-013Ashland5IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2016-012Centrahoma62IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2016-011Gerty7IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2016-010Powell Corner 115kV Substation90IA FULLY EXECUTED/ON SUSPENSION
2026-07-16SPPASGI-2016-004Canyon10IA FULLY EXECUTED/ON SCHEDULE
2026-07-16SPPASGI-2016-003Osawatomie12IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2015-004NowataReciprocating Combustion Engine56IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2015-001Pratt County6IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2014-014Payne County56IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2013-005Curry County2IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2013-004Finney County37IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2013-001Carson County12IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2012-008Arcadia4IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2012-006Hugoton22None
2026-07-16SPPASGI-2012-002Grady18IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2011-004Crosby County20IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2011-003Crosby10IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2011-002Hutchinson20IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2011-001Lovington27IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2010-021Lovington15IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2010-020Lovington30IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-16SPPASGI-2010-010Lovington42IA FULLY EXECUTED/COMMERCIAL OPERATION
2026-07-09SPPGEN-2026-SR24Barber120SPECIAL STUDY
2026-07-09SPPGEN-2026-SR23Johnston200SPECIAL STUDY
2026-06-26SPPGEN-2026-SR22Oxford150SPECIAL STUDY
2026-06-18SPPGEN-2026-SR21South Coffeyville148SPECIAL STUDY

Capacity revisions

ObservedISOProjectCountyWasNow
2026-07-16SPPGEN-2025-SR13Konawa130125

No longer listed

ObservedISOProjectCountyLast published status
2026-07-02SPP23-05032Fort CollinsDISIS STAGE
2026-06-18SPPGEN-2026-PR3Garfield CountySPECIAL STUDY
2026-06-18SPPGEN-2024-SR12La Moure CountyIA PENDING
2026-06-18SPP2023-G5.2Coconino CountyDISIS STAGE

Where each number came from

ISOWe last readSource last changedSource
SPP2026-08-062026-08-06 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.