Interconnection queue › Changes › Nebraska
2026-06-11 → 2026-08-25 · every difference we have observed, not just this week's
We have recorded 25 changes across 18 projects in the Nebraska queue since 2026-06-11: 0 new entries, 11 status changes, 8 in-service dates moved (8 of them later), 0 capacity revisions and 6 projects no longer listed.
| Snapshot | Changes observed |
|---|---|
| 2026-08-12 | 6 |
| 2026-08-06 | 2 |
| 2026-07-02 | 4 |
| 2026-06-25 | 3 |
| 2026-06-18 | 10 |
Get told what moves in Nebraska
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Nebraska: what entered, what moved study phase, what came off the list.
Email me Nebraska queue changes →Work email only. No newsletter, no obligation.
| Observed | ISO | Project | County | Was | Now |
|---|---|---|---|---|---|
| 2026-08-06 | SPP | GEN-2024-SR10 | Lancaster | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-07-02 | SPP | GEN-2023-153 | Perkins | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-25 | SPP | GEN-2023-SR19 | Jefferson County | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-25 | SPP | GEN-2021-108 | Cass | IA FULLY EXECUTED/ON SCHEDULE | IA FULLY EXECUTED/ON SUSPENSION |
| 2026-06-18 | SPP | GEN-2023-225 | Lancaster | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-18 | SPP | GEN-2023-224 | Lancaster | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-18 | SPP | GEN-2023-223 | Gage | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-18 | SPP | GEN-2023-222 | Gage | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-18 | SPP | GEN-2023-079 | Cass | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-18 | SPP | GEN-2023-078 | Cass | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-18 | SPP | GEN-2023-077 | Cass | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
The date a project told its ISO it would start commercial operation, against what the same project published at the previous snapshot. A date appearing for the first time is not counted here — there is no earlier plan for it to have moved from.
| Observed | ISO | Project | MW | Was | Now | Moved |
|---|---|---|---|---|---|---|
| 2026-08-06 | SPP | GEN-2024-SR10 | 80 | 12/31/2026 | 11/1/2027 | 305 days later |
| 2026-07-02 | SPP | GEN-2023-223 | 239 | 6/1/2030 | 6/1/2033 | 1,096 days later |
| 2026-07-02 | SPP | GEN-2023-222 | 478 | 6/1/2030 | 6/1/2033 | 1,096 days later |
| 2026-07-02 | SPP | GEN-2023-153 | 120 | 8/31/2028 | 11/1/2029 | 427 days later |
| 2026-06-25 | SPP | GEN-2023-SR19 | 50 | 9/8/2026 | 11/1/2027 | 419 days later |
| 2026-06-18 | SPP | GEN-2023-078 | 255 | 2/1/2028 | 9/22/2028 | 234 days later |
| 2026-06-18 | SPP | GEN-2023-077 | 255 | 2/1/2028 | 9/22/2028 | 234 days later |
| 2026-06-18 | SPP | IFS-2017-002-73 | 115 | 12/31/2024 | 7/1/2028 | 1,278 days later |
| Observed | ISO | Project | County | Last published status |
|---|---|---|---|---|
| 2026-08-12 | SPP | GEN-2024-374 | Scotts Bluff | DISIS STAGE |
| 2026-08-12 | SPP | GEN-2024-173 | Lancaster | DISIS STAGE |
| 2026-08-12 | SPP | GEN-2024-168 | Fillmore | DISIS STAGE |
| 2026-08-12 | SPP | GEN-2024-162 | Dakota | DISIS STAGE |
| 2026-08-12 | SPP | GEN-2024-140 | Mercer | DISIS STAGE |
| 2026-08-12 | SPP | GEN-2024-051 | Lancaster | DISIS STAGE |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| SPP | 2026-08-25 | 2026-08-25 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.