What Has Changed in the Oklahoma Interconnection Queue
2026-06-11 → 2026-09-07 · every difference we have observed, not just this week's
We have recorded 39 changes across 29 projects in the Oklahoma queue since 2026-06-11: 10 new entries, 14 status changes, 13 in-service dates moved (10 of them later), 1 capacity revisions and 1 projects no longer listed.
- SPP enters our archive on 2026-08-14 with 1,022 projects. That is our collection starting, not projects entering the queue, so none of those rows is counted as an arrival here. We have no earlier copy to have seen them absent from.
- SPP is not observed from 2026-08-13 onward; we last read it on 2026-08-12, when it carried 1,020 projects. Those rows are excluded rather than counted as departures. A queue we did not fetch has not emptied.
When it moved
| Snapshot | Changes observed |
|---|---|
| 2026-09-04 | 2 |
| 2026-09-03 | 1 |
| 2026-09-02 | 1 |
| 2026-09-01 | 1 |
| 2026-08-10 | 2 |
| 2026-08-06 | 7 |
| 2026-07-16 | 11 |
| 2026-07-09 | 1 |
| 2026-07-02 | 6 |
| 2026-06-25 | 1 |
| 2026-06-18 | 6 |
See what moved in Oklahoma each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in Oklahoma, from new entries to projects that came off the list.
Email me Oklahoma queue changesWork email only. No newsletter, no obligation.
Status changes
| Observed | ISO | Project | County | Was | Now |
|---|---|---|---|---|---|
| 2026-09-04 | SPP | IFS-2016-002-01 | Pontotoc | IA FULLY EXECUTED/ON SCHEDULE | IA FULLY EXECUTED/COMMERCIAL OPERATION |
| 2026-09-03 | SPP | ERAS-2025-009 | Chouteau | ERAS | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-08-10 | SPP | GEN-2023-038 | Coal | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-08-06 | SPP | GEN-2023-210 | Lincoln | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-08-06 | SPP | IFS-2017-001-15 | Mayes County | IA FULLY EXECUTED/ON SCHEDULE | IA FULLY EXECUTED/COMMERCIAL OPERATION |
| 2026-08-06 | SPP | IFS-2017-001-14 | Mayes County | IA FULLY EXECUTED/ON SCHEDULE | IA FULLY EXECUTED/COMMERCIAL OPERATION |
| 2026-07-16 | SPP | GEN-2022-136 | Bryan | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-07-16 | SPP | GEN-2021-025 | Woodward | IA FULLY EXECUTED/ON SCHEDULE | IA FULLY EXECUTED/ON SUSPENSION |
| 2026-07-02 | SPP | GEN-2021-025 | Woodward | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-25 | SPP | GEN-2024-SR6 | Johnston County | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-18 | SPP | GEN-2023-177 | Garvin | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-18 | SPP | GEN-2023-161 | Blaine | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-18 | SPP | GEN-2023-102 | Woods | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
| 2026-06-18 | SPP | GEN-2023-088 | Okfuskee/Okmulgee | IA PENDING | IA FULLY EXECUTED/ON SCHEDULE |
In-service dates that moved
The date a project told its ISO it would start commercial operation, against what the same project published at the previous snapshot. A date appearing for the first time is not counted here, because there is no earlier plan for it to have moved from.
| Observed | ISO | Project | MW | Was | Now | Moved |
|---|---|---|---|---|---|---|
| 2026-09-04 | SPP | IFS-2016-002-01 | 148 | 12/19/2025 | 1/13/2026 | 25 days later |
| 2026-09-02 | SPP | IFS-2017-002-69 | 72 | 12/1/2027 | 5/1/2028 | 152 days later |
| 2026-09-01 | SPP | GEN-2018-048 | 300 | 6/15/2028 | 6/15/2029 | 365 days later |
| 2026-08-10 | SPP | GEN-2023-038 | 200 | 9/1/2026 | 9/1/2029 | 1,096 days later |
| 2026-08-06 | SPP | GEN-2023-210 | 191 | 9/1/2026 | 9/1/2029 | 1,096 days later |
| 2026-08-06 | SPP | IFS-2017-001-18 | 125 | 6/6/2026 | 5/6/2026 | 31 days earlier |
| 2026-08-06 | SPP | IFS-2017-001-15 | 72 | 6/22/2026 | 8/3/2026 | 42 days later |
| 2026-08-06 | SPP | IFS-2017-001-14 | 72 | 5/8/2026 | 8/2/2026 | 86 days later |
| 2026-07-02 | SPP | GEN-2023-177 | 200 | 6/1/2028 | 9/1/2029 | 457 days later |
| 2026-07-02 | SPP | GEN-2023-102 | 475 | 6/30/2029 | 3/1/2029 | 121 days earlier |
| 2026-07-02 | SPP | GEN-2023-088 | 117 | 12/31/2028 | 9/29/2028 | 93 days earlier |
| 2026-07-02 | SPP | GEN-2022-154 | 100 | 7/15/2029 | 9/19/2029 | 66 days later |
| 2026-07-02 | SPP | GEN-2021-025 | 203 | 12/1/2026 | 5/3/2029 | 884 days later |
New queue entries
| Observed | ISO | Project | County | Fuel | MW | Status |
|---|---|---|---|---|---|---|
| 2026-07-16 | SPP | GEN-2026-SR27 | Muskogee | — | 300 | SPECIAL STUDY |
| 2026-07-16 | SPP | ASGI-2024-006 | Texas | Solar/Storage | 100 | None |
| 2026-07-16 | SPP | ASGI-2024-002 | Boise City | Solar/Battery | 30 | None |
| 2026-07-16 | SPP | ASGI-2016-013 | Ashland | — | 5 | IA FULLY EXECUTED/COMMERCIAL OPERATION |
| 2026-07-16 | SPP | ASGI-2016-012 | Centrahoma | — | 62 | IA FULLY EXECUTED/COMMERCIAL OPERATION |
| 2026-07-16 | SPP | ASGI-2016-011 | Gerty | — | 7 | IA FULLY EXECUTED/COMMERCIAL OPERATION |
| 2026-07-16 | SPP | ASGI-2015-004 | Nowata | Reciprocating Combustion Engine | 56 | IA FULLY EXECUTED/COMMERCIAL OPERATION |
| 2026-07-16 | SPP | ASGI-2014-014 | Payne County | — | 56 | IA FULLY EXECUTED/COMMERCIAL OPERATION |
| 2026-07-09 | SPP | GEN-2026-SR23 | Johnston | — | 200 | SPECIAL STUDY |
| 2026-06-18 | SPP | GEN-2026-SR21 | South Coffeyville | — | 148 | SPECIAL STUDY |
Capacity revisions
| Observed | ISO | Project | County | Was | Now |
|---|---|---|---|---|---|
| 2026-07-16 | SPP | GEN-2025-SR13 | Konawa | 130 | 125 |
No longer listed
| Observed | ISO | Project | County | Last published status |
|---|---|---|---|---|
| 2026-06-18 | SPP | GEN-2026-PR3 | Garfield County | SPECIAL STUDY |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| SPP | 2026-09-07 | 2026-09-05 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.