Interconnection queue › Massachusetts › Berkshire County
Snapshot of 2026-08-06 · 42 projects · Massachusetts (MA)
There are 42 projects in the interconnection queue located in Berkshire County, Massachusetts (MA), totalling 2,767 MW across the 40 that publish a capacity.
Get told what moves in Berkshire County, Massachusetts
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Berkshire County, Massachusetts: what entered, what moved study phase, what came off the list.
Email me Berkshire County, Massachusetts queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| ISO-NE | 42 | 2,767 MW |
Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here — the national table is the only place any fuel code is mapped.
| Fuel | Projects | Capacity |
|---|---|---|
| BAT | 8 | 1,165 MW |
| SUN BAT | 8 | 40 MW |
| WAT | 7 | 152 MW |
| WND | 5 | 40 MW |
| N/A | 5 | 1,200 MW |
| SUN | 4 | 38 MW |
| WDS | 3 | 112 MW |
| DFO NG | 2 | 20 MW |
| Status | Projects | Capacity |
|---|---|---|
| (not published) | 42 | 2,767 MW |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| HVDC from NY to WMA - bidirectional | ISO-NE | 600 | not published | 2/16/2015 | 8/30/2019 |
| AC tie line (import only) | ISO-NE | 600 | not published | 5/11/2017 | 12/31/2023 |
| Battery Storage | ISO-NE | 290 | not published | 4/9/2024 | 8/30/2028 |
| Battery Storage | ISO-NE | 200 | not published | 12/30/2021 | 12/31/2024 |
| Battery Storage | ISO-NE | 170 | not published | 5/30/2024 | 12/31/2029 |
| Battery Storage | ISO-NE | 136 | not published | 4/9/2024 | 8/30/2028 |
| Battery Storage | ISO-NE | 130 | not published | 11/22/2022 | 12/31/2026 |
| Battery Storage | ISO-NE | 119 | not published | 9/23/2022 | 10/31/2025 |
| Battery Storage | ISO-NE | 100 | not published | 4/26/2023 | 12/31/2026 |
| Bear Swamp Unit 1 and 2 Upgrade | ISO-NE | 66 | not published | 1/21/2016 | 1/6/2023 |
| Biomass Project ( Also see queue position #223) | ISO-NE | 62 | not published | 6/27/2007 | 12/1/2010 |
| Biomass Project | ISO-NE | 50 | not published | 1/30/2009 | 10/1/2013 |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| ISO-NE | 2026-08-06 | 2026-08-06 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.