Interconnection queueMassachusetts › Bristol County

Bristol County, Massachusetts Interconnection Queue

Snapshot of 2026-08-06 · 65 projects · Massachusetts (MA)

There are 65 projects in the interconnection queue located in Bristol County, Massachusetts (MA), totalling 7,799 MW across the 56 that publish a capacity.

Technology in Bristol County

Get told what moves in Bristol County, Massachusetts

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Bristol County, Massachusetts: what entered, what moved study phase, what came off the list.

Email me Bristol County, Massachusetts queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
ISO-NE657,799 MW (from 56 of 65 projects)

By fuel, as published

Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here — the national table is the only place any fuel code is mapped.

FuelProjectsCapacity
BAT264,436 MW
SUN BAT16170 MW
(not published)5not published
BIT536 MW (from 4 of 5 projects)
SUN416 MW
N/A32,800 MW (from 2 of 3 projects)
NG25 MW (from 1 of 2 projects)
DFO NG2244 MW (from 1 of 2 projects)
KER NG124 MW
NG WO168 MW

By status, as published

StatusProjectsCapacity
(not published)657,799 MW (from 56 of 65 projects)

Largest projects with published capacity

The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.

ProjectISOMWStatusQueue dateProposed operation
345 kV AC line
ID 625
ISO-NE1,600not published11/10/201612/31/2023
Somerset Wind Link - 1200 MW HVDC Line (Controllable) into Brayton Point
ID 837
ISO-NE1,200not published2/22/201912/31/2031
Battery Storage
ID 1426
ISO-NE529not published7/14/20233/31/2028
Battery Storage
ID 1460
ISO-NE350not published10/12/20239/30/2027
Battery Storage
ID 1340
ISO-NE293not published12/6/20226/30/2027
Battery Storage
ID 1367
ISO-NE271not published3/9/20234/1/2027
Battery Storage
ID 1339
ISO-NE257not published12/6/20226/30/2027
Energy Storage
ID 876
ISO-NE246not published4/11/201912/31/2024
Combined Cycle
ID 216
ISO-NE244not published6/8/200712/31/2013
Storage
ID 1198
ISO-NE242not published12/30/20215/12/2028
Battery Storage
ID 1430
ISO-NE238not published8/9/202310/17/2027
Battery Storage
ID 1335
ISO-NE206not published11/10/20224/1/2027

Where each number came from

ISOWe last readSource last changedSource
ISO-NE2026-08-062026-08-06 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.

Interconnection queue home · This week's changes · How this is collected · US Tech Automations.