Interconnection queue › Massachusetts › Hampden County
Snapshot of 2026-08-06 · 68 projects · Massachusetts (MA)
There are 68 projects in the interconnection queue located in Hampden County, Massachusetts (MA), totalling 6,307 MW across the 62 that publish a capacity.
Get told what moves in Hampden County, Massachusetts
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Hampden County, Massachusetts: what entered, what moved study phase, what came off the list.
Email me Hampden County, Massachusetts queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| ISO-NE | 68 | 6,307 MW |
Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here — the national table is the only place any fuel code is mapped.
| Fuel | Projects | Capacity |
|---|---|---|
| BAT | 22 | 3,161 MW |
| SUN | 11 | 112 MW |
| DFO NG | 7 | 2,311 MW |
| WAT | 7 | 6 MW |
| SUN BAT | 5 | 26 MW |
| NG | 4 | 9 MW |
| (not published) | 3 | not published |
| WDS | 2 | 92 MW |
| WND | 2 | 35 MW |
| NG RFO | 1 | not published |
| DFO KER NG | 1 | 156 MW |
| BIT | 1 | not published |
| N/A | 1 | 395 MW |
| FC | 1 | 4 MW |
| Status | Projects | Capacity |
|---|---|---|
| (not published) | 68 | 6,307 MW |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| Combined Cycle | ISO-NE | 837 | not published | 12/10/2014 | 6/1/2019 |
| Combined cycle (alt to Q442/472) | ISO-NE | 431 | not published | 3/2/2015 | 3/1/2019 |
| Regional Network Service Request | ISO-NE | 395 | not published | 6/3/2021 | 10/1/2023 |
| Combined Cycle | ISO-NE | 388 | not published | 2/26/2014 | 3/1/2019 |
| Pioneer Valley Energy Center | ISO-NE | 353 | not published | 11/30/2007 | 9/28/2015 |
| Battery Storage | ISO-NE | 301 | not published | 3/1/2023 | 11/20/2026 |
| Battery Storage | ISO-NE | 300 | not published | 11/2/2022 | 12/23/2025 |
| Combined Cycle | ISO-NE | 280 | not published | 10/13/2006 | 7/1/2015 |
| Battery Storage | ISO-NE | 275 | not published | 12/6/2022 | 6/30/2027 |
| Battery Storage | ISO-NE | 251 | not published | 4/8/2024 | 12/31/2027 |
| Battery Storage | ISO-NE | 250 | not published | 3/9/2023 | 6/30/2029 |
| Streamfield | ISO-NE | 202 | not published | 4/15/2021 | 5/31/2027 |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| ISO-NE | 2026-08-06 | 2026-08-06 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.