Interconnection queueNew Hampshire › Coos County

Coos County, New Hampshire Interconnection Queue

Snapshot of 2026-08-06 · 32 projects · New Hampshire (NH)

There are 32 projects in the interconnection queue located in Coos County, New Hampshire (NH), totalling 956 MW across the 23 that publish a capacity.

Get told what moves in Coos County, New Hampshire

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Coos County, New Hampshire: what entered, what moved study phase, what came off the list.

Email me Coos County, New Hampshire queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
ISO-NE32956 MW (from 23 of 32 projects)

By fuel, as published

Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here — the national table is the only place any fuel code is mapped.

FuelProjectsCapacity
WND8487 MW
WDS797 MW (from 3 of 7 projects)
SUN7230 MW
N/A30 MW (from 1 of 3 projects)
(not published)2not published
WAT1not published
LFG16 MW
NG18 MW
WAT BAT115 MW
SUN BAT1113 MW

By status, as published

StatusProjectsCapacity
(not published)32956 MW (from 23 of 32 projects)

Largest projects with published capacity

The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.

ProjectISOMWStatusQueue dateProposed operation
Wind
ID 280
ISO-NE180not published10/2/20089/1/2011
Wind
ID 176
ISO-NE146not published10/20/200612/30/2008
Solar + Battery Storage
ID 1135
ISO-NE113not published5/13/20215/15/2025
Granite Reliable Power
ID 166
ISO-NE94not published8/9/20062/15/2012
Solar
ID 1034
ISO-NE60not published6/29/202012/30/2023
Solar
ID 1035
ISO-NE60not published6/29/202012/30/2023
Burgess BioPower
ID 251
ISO-NE59not published2/15/20086/17/2014
Solar
ID 936
ISO-NE45not published10/30/201910/1/2024
Wind Project
ID 200
ISO-NE34not published2/21/200711/1/2014
CPD Berlin
ID 229#d74c5e08
ISO-NE30not published10/15/20078/31/2013
Solar
ID 1164
ISO-NE20not published9/23/202111/1/2023
Solar
ID 685
ISO-NE20not published10/20/20177/1/2022

Where each number came from

ISOWe last readSource last changedSource
ISO-NE2026-08-062026-08-06 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.

Interconnection queue home · This week's changes · How this is collected · US Tech Automations.