Interconnection queueNew Hampshire › Rockingham County

Rockingham County, New Hampshire Interconnection Queue

Snapshot of 2026-08-06 · 25 projects · New Hampshire (NH)

There are 25 projects in the interconnection queue located in Rockingham County, New Hampshire (NH), totalling 4,626 MW across the 18 that publish a capacity.

Get told what moves in Rockingham County, New Hampshire

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Rockingham County, New Hampshire: what entered, what moved study phase, what came off the list.

Email me Rockingham County, New Hampshire queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
ISO-NE254,626 MW (from 18 of 25 projects)

By fuel, as published

Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here — the national table is the only place any fuel code is mapped.

FuelProjectsCapacity
NG61,590 MW
SUN4130 MW
(not published)3not published
NUC313 MW (from 2 of 3 projects)
N/A32,290 MW (from 2 of 3 projects)
DFO NG20 MW (from 1 of 2 projects)
BAT2602 MW
JF NG1not published
KER BAT11 MW

By status, as published

StatusProjectsCapacity
(not published)254,626 MW (from 18 of 25 projects)

Largest projects with published capacity

The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.

ProjectISOMWStatusQueue dateProposed operation
HVDC/AC Tie - Import only
ID 519
ISO-NE1,200not published2/16/20154/30/2019
Northern Pass Transmission Project (300 kV HVDC/AC Tie) - Import Only
ID 499
ISO-NE1,090not published2/16/201512/29/2022
Combined Cycle Capacity Increase/ Generator Change
ID 226
ISO-NE904not published9/5/20076/30/2013
Combined Cycle( See # 226)
ID 165
ISO-NE563not published8/3/20066/30/2013
Battery Storage
ID 1364
ISO-NE402not published3/1/202311/20/2026
Battery Storage
ID 1443
ISO-NE200not published9/20/202312/30/2026
Solar
ID 1428
ISO-NE100not published7/25/202312/30/2028
GRE Capacity Uprate
ID 481
ISO-NE41not published11/18/20146/29/2017
Combined Cycle Increase
ID 479
ISO-NE33not published10/17/20143/8/2015
Newington Gas Turbine Uprate
ID 484
ISO-NE28not published12/4/201410/30/2015
EP Newington Energy Capacity Increase
ID 414
ISO-NE21not published3/26/20136/17/2014
Seabrook LP Turbine Blade replacement
ID 284
ISO-NE13not published10/22/20084/5/2012

Where each number came from

ISOWe last readSource last changedSource
ISO-NE2026-08-062026-08-06 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.

Interconnection queue home · This week's changes · How this is collected · US Tech Automations.