Snapshot of 2026-07-30 · 2,278 projects

The CAISO queue currently lists 2,278 projects, totalling 492,197 MW across the 2,278 of them that publish a capacity.

Not published by CAISO in this report: proposed commercial operation date.

By fuel, as published

Reproduced using CAISO's own codes. The national table maps these onto shared buckets; this one does not.

FuelProjectsCapacity
Solar1,051173,918 MW
Battery672161,768 MW
Natural Gas24874,615 MW
Wind Turbine20963,448 MW
Geothermal352,966 MW
Biofuel21341 MW
Water156,433 MW
Other81,268 MW
Pumped-Storage hydro76,200 MW
(not published)51,014 MW
Flywheel371 MW
Nuclear3113 MW
Gravity via Rail144 MW

By status, as published

CAISO uses its own status vocabulary. We reproduce it exactly โ€” mapping it onto a shared 'active / withdrawn' scale would be us asserting something the ISO did not.

StatusProjectsCapacity
WITHDRAWN1,760381,307 MW
ACTIVE26976,037 MW
COMPLETED24934,853 MW

Get told what moves in CAISO

The ISOs publish today's queue and overwrite it โ€” no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in CAISO: what entered, what moved study phase, what came off the list.

Email me CAISO queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

Top states

StateProjectsCapacity
California2,076416,846 MW
Nevada10426,986 MW
Arizona7232,962 MW
MX188,772 MW
(not published)480 MW
Idaho21,850 MW
New Mexico11,700 MW
Wyoming13,000 MW

Top counties

CountyProjectsCapacity
KERN37065,200 MW
FRESNO20826,568 MW
SAN DIEGO20328,419 MW
SAN BERNARDINO15945,117 MW
LOS ANGELES14231,256 MW
RIVERSIDE14046,640 MW
KINGS9012,271 MW
SAN JOAQUIN5911,553 MW
CLARK5518,085 MW
IMPERIAL5415,015 MW
ALAMEDA538,513 MW
CONTRA COSTA5211,264 MW
MERCED486,729 MW
SAN LUIS OBISPO4525,358 MW
TULARE446,656 MW

Where each number came from

ISOWe last readSource last changedSource
CAISO2026-07-302026-07-30 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.

Interconnection queue home · This week's changes · How this is collected · US Tech Automations.