Interconnection queue › Connecticut › Fairfield County
Snapshot of 2026-08-06 · 63 projects · Connecticut (CT)
There are 63 projects in the interconnection queue located in Fairfield County, Connecticut (CT), totalling 7,045 MW across the 41 that publish a capacity.
Get told what moves in Fairfield County, Connecticut
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Fairfield County, Connecticut: what entered, what moved study phase, what came off the list.
Email me Fairfield County, Connecticut queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| ISO-NE | 63 | 7,045 MW |
Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here — the national table is the only place any fuel code is mapped.
| Fuel | Projects | Capacity |
|---|---|---|
| NG | 22 | 2,270 MW |
| DFO NG | 15 | 2,162 MW |
| (not published) | 11 | not published |
| DFO | 5 | 514 MW |
| BAT | 4 | 567 MW |
| KER | 2 | 322 MW |
| N/A | 2 | 1,200 MW |
| DFO SUB | 1 | 5 MW |
| SUN | 1 | 5 MW |
| Status | Projects | Capacity |
|---|---|---|
| (not published) | 63 | 7,045 MW |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| 1200 MW HVDC Line into Singer (Controllable) | ISO-NE | 1,200 | not published | 7/29/2019 | 9/1/2024 |
| Combined Cycle | ISO-NE | 745 | not published | 6/8/2011 | 6/1/2016 |
| Combined Cycle | ISO-NE | 695 | not published | 9/12/2008 | 6/1/2013 |
| Combined Cycle | ISO-NE | 680 | not published | 1/13/2012 | 5/31/2016 |
| PSEG Bridgeport Harbor CCGT Expansion | ISO-NE | 510 | not published | 2/28/2013 | 6/10/2019 |
| Gas Turbine | ISO-NE | 325 | not published | 6/30/2006 | 9/30/2010 |
| Norwalk Harbor Station Redevelopment | ISO-NE | 322 | not published | 11/2/2004 | 2/28/2013 |
| Combined Cycle | ISO-NE | 269 | not published | 3/11/2008 | 6/1/2011 |
| Combustion Turbine | ISO-NE | 245 | not published | 3/4/2014 | 5/31/2018 |
| Gas Turbine | ISO-NE | 233 | not published | 5/3/2023 | 6/1/2026 |
| Waterside Power - 180 MW | ISO-NE | 204 | not published | 3/6/2003 | 12/31/2011 |
| Battery Storage | ISO-NE | 201 | not published | 3/9/2023 | 11/20/2026 |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| ISO-NE | 2026-08-06 | 2026-08-06 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.