Interconnection queue › Connecticut › Fairfield County › Gas
Snapshot of 2026-08-06 · 22 projects
22 gas projects are in the interconnection queue in Fairfield County, Connecticut, totalling 2,270 MW across the 16 that publish a capacity.
Get told what moves in gas in Fairfield County, Connecticut
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in gas in Fairfield County, Connecticut: what entered, what moved study phase, what came off the list.
Email me gas in Fairfield County, Connecticut queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| ISO-NE | 22 | 2,270 MW |
| Fuel | Projects | Capacity |
|---|---|---|
| NG | 22 | 2,270 MW |
| Status | Projects |
|---|---|
| (not published) | 22 |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| Combined Cycle | ISO-NE | 745 | not published | 6/8/2011 | 6/1/2016 |
| Combined Cycle | ISO-NE | 680 | not published | 1/13/2012 | 5/31/2016 |
| Gas Turbine | ISO-NE | 325 | not published | 6/30/2006 | 9/30/2010 |
| Gas Turbine | ISO-NE | 233 | not published | 5/3/2023 | 6/1/2026 |
| Combustion Turbine | ISO-NE | 102 | not published | 4/25/2016 | 6/1/2019 |
| Bridgeport Energy Uprate | ISO-NE | 84 | not published | 6/16/2014 | 6/5/2015 |
| Fuel Cell | ISO-NE | 29 | not published | 12/5/2006 | 6/1/2009 |
| Bridgeport Energy Wet Compression Upgrade | ISO-NE | 18 | not published | 2/26/2015 | 6/1/2018 |
| Fuel Cell | ISO-NE | 14 | not published | 6/16/2006 | 6/1/2009 |
| Sikorsky Aircraft | ISO-NE | 10 | not published | 1/8/2009 | 10/5/2011 |
| Fuel Cell | ISO-NE | 10 | not published | 1/23/2020 | 12/1/2024 |
| Bridgeport Fuel Cell I | ISO-NE | 6 | not published | 7/25/2012 | 12/22/2013 |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| ISO-NE | 2026-08-06 | 2026-08-06 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.