Interconnection queue › Rhode Island › Washington County
Snapshot of 2026-08-06 · 31 projects · Rhode Island (RI)
There are 31 projects in the interconnection queue located in Washington County, Rhode Island (RI), totalling 1,900 MW across the 31 that publish a capacity.
Get told what moves in Washington County, Rhode Island
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Washington County, Rhode Island: what entered, what moved study phase, what came off the list.
Email me Washington County, Rhode Island queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| ISO-NE | 31 | 1,900 MW |
Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here — the national table is the only place any fuel code is mapped.
| Fuel | Projects | Capacity |
|---|---|---|
| SUN | 23 | 204 MW |
| WND | 5 | 998 MW |
| BAT | 3 | 698 MW |
| Status | Projects | Capacity |
|---|---|---|
| (not published) | 31 | 1,900 MW |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| Wind | ISO-NE | 536 | not published | 2/10/2010 | 12/31/2015 |
| Wind | ISO-NE | 385 | not published | 5/27/2008 | 12/1/2012 |
| Battery Storage | ISO-NE | 313 | not published | 6/12/2024 | 1/31/2027 |
| Battery Storage | ISO-NE | 205 | not published | 9/22/2021 | 12/7/2029 |
| Battery Storage | ISO-NE | 180 | not published | 4/1/2019 | 3/1/2023 |
| Wood River Substation - Western RI DER Study #3 | ISO-NE | 49 | not published | 8/19/2024 | 12/31/2026 |
| Wood River - NG WRI DG Area Study #2 >5 MW | ISO-NE | 34 | not published | 8/19/2020 | 6/30/2025 |
| Block Island Wind Farm | ISO-NE | 29 | not published | 1/18/2013 | 12/9/2016 |
| Wind | ISO-NE | 29 | not published | 8/28/2009 | 12/31/2012 |
| Wind | ISO-NE | 20 | not published | 2/5/2009 | 6/30/2012 |
| Alton Solar | ISO-NE | 14 | not published | 11/20/2017 | 4/30/2020 |
| Wood River - NG WRI DG Area Study #2 <5 MW | ISO-NE | 10 | not published | 8/19/2020 | 6/30/2025 |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| ISO-NE | 2026-08-06 | 2026-08-06 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.