Interconnection queue › Nevada › Geothermal
Geothermal Projects in the Nevada Interconnection Queue
Snapshot of 2026-09-07 · 19 projects
19 geothermal projects are in the interconnection queue with a Nevada location, totaling 1,509 MW across the 19 that publish a capacity.
See what moved in geothermal in Nevada each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in geothermal in Nevada, from new entries to projects that came off the list.
Email me geothermal in Nevada queue changesWork email only. No newsletter, no obligation.
By ISO
| ISO | Projects | Capacity |
|---|---|---|
| CAISO | 19 | 1,509 MW |
By status, as published
| Status | Projects |
|---|---|
| WITHDRAWN | 18 |
| COMPLETED | 1 |
Top counties
| County | Projects | Capacity |
|---|---|---|
| CHURCHILL | 13 | 552 MW |
| MINERAL | 3 | 239 MW |
| ESMERALDA COUNTY | 2 | 627 MW |
| CHURCH | 1 | 90 MW |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | County | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|---|
| ALUM GEOTHERMAL | CAISO | ESMERALDA COUNTY | 427 | WITHDRAWN | 2021-04-15 | not published |
| PEARL GEOTHERMAL | CAISO | ESMERALDA COUNTY | 200 | WITHDRAWN | 2021-04-15 | not published |
| GREEN BORDERS GEOTHERMAL PHASE 2 | CAISO | MINERAL | 150 | WITHDRAWN | 2007-03-06 | not published |
| GREEN BORDERS GEOTHERMAL PHASE II | CAISO | CHURCH | 90 | WITHDRAWN | 2006-11-16 | not published |
| COYOTE CANYON | CAISO | CHURCHILL | 70 | WITHDRAWN | 2011-03-31 | not published |
| GREEN BORDERS GEOTHERMAL | CAISO | MINERAL | 62 | WITHDRAWN | 2005-02-22 | not published |
| NYC #1 | CAISO | CHURCHILL | 61 | WITHDRAWN | 2008-05-29 | not published |
| DIXIE MEADOWS #1 | CAISO | CHURCHILL | 61 | WITHDRAWN | 2008-05-29 | not published |
| TGDV #1 | CAISO | CHURCHILL | 61 | WITHDRAWN | 2008-05-29 | not published |
| TGDV#2 | CAISO | CHURCHILL | 61 | WITHDRAWN | 2008-05-29 | not published |
| NYC #2 | CAISO | CHURCHILL | 52 | WITHDRAWN | 2008-05-29 | not published |
| DIXIE MEADOWS #2 | CAISO | CHURCHILL | 52 | WITHDRAWN | 2008-05-29 | not published |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| CAISO | 2026-09-07 | 2026-09-07 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.