Interconnection queueNevada › Solar

Solar Projects in the Nevada Interconnection Queue

Snapshot of 2026-07-30 · 53 projects

53 solar projects are in the interconnection queue with a Nevada location, totalling 11,665 MW across the 53 that publish a capacity.

Grouped from the ISOs' own fuel codes — see the mapping. Codes we could not match to a published definition are left unclassified rather than assigned here.

Get told what moves in solar in Nevada

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in solar in Nevada: what entered, what moved study phase, what came off the list.

Email me solar in Nevada queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
CAISO5311,665 MW

By status, as published

StatusProjects
WITHDRAWN41
ACTIVE6
COMPLETED6

Top counties

CountyProjectsCapacity
CLARK296,516 MW
NYE213,488 MW
LINCOLN1960 MW
SAN BENITO1400 MW
CLARK/NYE1300 MW

Where each number came from

ISOWe last readSource last changedSource
CAISO2026-07-302026-07-30 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.

Interconnection queue home · This week's changes · How this is collected · US Tech Automations.