Interconnection queue › Oklahoma › Gas
Gas Projects in the Oklahoma Interconnection Queue
Snapshot of 2026-09-07 · 27 projects
27 gas projects are in the interconnection queue with a Oklahoma location, totaling 11,198 MW across the 27 that publish a capacity.
See what moved in gas in Oklahoma each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in gas in Oklahoma, from new entries to projects that came off the list.
Email me gas in Oklahoma queue changesWork email only. No newsletter, no obligation.
By ISO
| ISO | Projects | Capacity |
|---|---|---|
| SPP | 27 | 11,198 MW |
By status, as published
| Status | Projects |
|---|---|
| DISIS STAGE | 10 |
| IA FULLY EXECUTED/COMMERCIAL OPERATION | 8 |
| ERAS | 6 |
| IA FULLY EXECUTED/ON SCHEDULE | 3 |
Top counties
| County | Projects | Capacity |
|---|---|---|
| Harrah | 3 | 1,767 MW |
| Kay | 2 | 224 MW |
| Oklahoma | 2 | 992 MW |
| Anadarko | 2 | 787 MW |
| Caddo County | 2 | 327 MW |
| Lawton | 2 | 1,488 MW |
| Pittsburgh | 1 | 1,045 MW |
| Creek | 1 | 1,400 MW |
| Choctaw | 1 | 357 MW |
| Seminole | 1 | 493 MW |
| La Flore | 1 | 136 MW |
| McClain | 1 | 496 MW |
| Oklahoma City | 1 | 94 MW |
| Canadian | 1 | 24 MW |
| Mayes | 1 | 538 MW |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | County | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|---|
| GEN-2024-340 | SPP | Creek | 1,400 | DISIS STAGE | 3/1/2025 | 1/1/2032 |
| GEN-2024-341 | SPP | Pittsburgh | 1,045 | DISIS STAGE | 3/1/2025 | 11/10/2031 |
| ERAS-2025-004 | SPP | Harrah | 779 | ERAS | 9/30/2025 | 1/1/2030 |
| ERAS-2025-024 | SPP | Lawton | 744 | ERAS | 10/2/2025 | 11/30/2029 |
| ERAS-2025-026 | SPP | Lawton | 744 | ERAS | 10/2/2025 | 11/30/2029 |
| GEN-2024-299 | SPP | Oklahoma | 744 | DISIS STAGE | 3/1/2025 | 5/1/2032 |
| GEN-2024-128 | SPP | Anadarko | 690 | DISIS STAGE | 3/1/2025 | 12/31/2030 |
| IFS-2013-002-03 | SPP | Mayes | 538 | IA FULLY EXECUTED/COMMERCIAL OPERATION | 9/30/2013 | 12/23/2017 |
| ERAS-2025-023 | SPP | Oologah | 510 | ERAS | 10/2/2025 | 12/15/2029 |
| ERAS-2025-010 | SPP | Harrah | 496 | ERAS | 9/10/2025 | 1/1/2029 |
| GEN-2024-013 | SPP | McClain | 496 | DISIS STAGE | 8/2/2024 | 1/1/2030 |
| GEN-2024-321 | SPP | Seminole | 493 | DISIS STAGE | 3/1/2025 | 4/30/2030 |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| SPP | 2026-09-07 | 2026-09-05 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.