Interconnection queueMassachusetts › Norfolk County

Norfolk County, Massachusetts Interconnection Queue

Snapshot of 2026-08-06 · 38 projects · Massachusetts (MA)

There are 38 projects in the interconnection queue located in Norfolk County, Massachusetts (MA), totalling 3,645 MW across the 32 that publish a capacity.

Get told what moves in Norfolk County, Massachusetts

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in Norfolk County, Massachusetts: what entered, what moved study phase, what came off the list.

Email me Norfolk County, Massachusetts queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
ISO-NE383,645 MW (from 32 of 38 projects)

By fuel, as published

Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here — the national table is the only place any fuel code is mapped.

FuelProjectsCapacity
BAT142,276 MW
DFO NG111,365 MW
NG5-21 MW (from 1 of 5 projects)
SUN BAT420 MW
(not published)2not published
N/A10 MW
SUN15 MW

By status, as published

StatusProjectsCapacity
(not published)383,645 MW (from 32 of 38 projects)

Largest projects with published capacity

The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.

ProjectISOMWStatusQueue dateProposed operation
Combined Cycle
ID 215
ISO-NE578not published5/30/20076/1/2013
Battery Storage Increase (QP1238)
ID 1362
ISO-NE301not published2/24/202311/12/2027
Battery Storage
ID 1238
ISO-NE300not published3/22/20224/28/2028
Battery Storage
ID 1327
ISO-NE270not published10/20/202212/2/2023
Battery Storage
ID 1523
ISO-NE254not published5/6/20246/1/2029
Battery Storage
ID 1444
ISO-NE250not published9/21/20239/15/2027
Medway Grid Battery Storage
ID 844
ISO-NE250not published3/13/20192/25/2026
Gas Turbine
ID 409
ISO-NE208not published2/28/20135/31/2018
Medway Peaker - SEMARI
ID 444
ISO-NE208not published5/2/20143/14/2019
Battery Storage
ID 886
ISO-NE200not published4/26/20195/31/2023
Energy Storage
ID 877
ISO-NE170not published4/11/20197/26/2027
Battery Storage Increase (QP1362)
ID 1373
ISO-NE140not published3/15/202311/12/2027

Where each number came from

ISOWe last readSource last changedSource
ISO-NE2026-08-062026-08-06 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.