Interconnection queue › New York › Clinton County
Clinton County, New York Interconnection Queue
Snapshot of 2026-09-07 · 26 projects · New York (NY)
There are 26 projects in the interconnection queue located in Clinton County, New York (NY), totaling 3,822 MW across the 24 that publish a capacity.
See what moved in Clinton County, New York each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in Clinton County, New York, from new entries to projects that came off the list.
Email me Clinton County, New York queue changesWork email only. No newsletter, no obligation.
By ISO
By fuel, as published
Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here. The national table is the only place any fuel code is mapped.
| Fuel | Projects | Capacity |
|---|---|---|
| ES | 7 | 875 MW |
| W | 5 | 903 MW |
| S | 5 | 205 MW |
| AC | 3 | 1,200 MW |
| (not published) | 2 | 150 MW |
| CR | 2 | 40 MW |
| BAT | 1 | 50 MW |
| DC | 1 | 400 MW |
By status, as published
| Status | Projects | Capacity |
|---|---|---|
| Withdrawn | 22 | 3,547 MW |
| (not published) | 2 | 50 MW |
| Cluster Study | 2 | 225 MW |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| Champlain Wind Link I | NYISO | 600 | Withdrawn | 2009-09-29 | not published |
| Champlain Wind Link II | NYISO | 600 | Withdrawn | 2009-09-29 | not published |
| Bull Run II Wind | NYISO | 449 | Withdrawn | 2015-12-15 | not published |
| Grand Isle Intertie | NYISO | 400 | Withdrawn | 2012-06-28 | not published |
| Bull Run Wind | NYISO | 304 | Withdrawn | 2015-04-24 | not published |
| Northline Energy Center | NYISO | 200 | Withdrawn | 2021-05-20 | not published |
| Marble River Storage | NYISO | 160 | Withdrawn | 2023-10-25 | not published |
| Orion Energy NY III | NYISO | 150 | Withdrawn | 2004-10-12 | not published |
| Valcour Storage | NYISO | 150 | Withdrawn | 2023-12-28 | not published |
| Valcour Storage | NYISO | 150 | Cluster Study | 2024-09-09 | 12-2028 |
| Bull Run Solar Energy Center | NYISO | 125 | Withdrawn | 2018-01-26 | not published |
| Lake City Storage | NYISO | 120 | Withdrawn | 2023-10-25 | not published |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| ISO-NE | 2026-09-07 | 2026-09-07 | source file |
| NYISO | 2026-09-07 | 2026-08-13 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.