Interconnection queueNew YorkHerkimer County › Solar

Solar Projects in Herkimer County, New York

Snapshot of 2026-08-06 · 16 projects

16 solar projects are in the interconnection queue in Herkimer County, New York, totalling 1,520 MW across the 16 that publish a capacity.

Grouped from the ISOs' own fuel codes — see the mapping. Codes we could not match to a published definition are left unclassified rather than assigned here.

Get told what moves in solar in Herkimer County, New York

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in solar in Herkimer County, New York: what entered, what moved study phase, what came off the list.

Email me solar in Herkimer County, New York queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
NYISO161,520 MW

By fuel code, as published

FuelProjectsCapacity
S161,520 MW

By status, as published

StatusProjects
Withdrawn11
Active5

Largest projects with published capacity

The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.

ProjectISOMWStatusQueue dateProposed operation
Diamond Solar
ID 1354
NYISO500Withdrawn2022-03-18not published
Columbia Solar Energy Center
ID 0857
NYISO350Withdrawn2019-05-28not published
Rocksdrift Energy Center
ID 1205
NYISO300Withdrawn2021-06-16not published
Goldenrod Solar
ID 0752
NYISO90Withdrawn2018-08-15not published
NY48 - Diamond Solar
ID 1174
NYISO60Withdrawn2021-05-17not published
Sabin Solar
ID 0454
NYISO20Withdrawn2014-08-20not published
Double Lock Solar
ID 0563
NYISO20Withdrawn2016-07-25not published
Hills Solar
ID 0581
NYISO20Active2025-11-2604-2028
Watkins Rd Solar
ID 0586
NYISO20Active2016-11-0802-2027
Sugar Maple Solar
ID 0613
NYISO20Withdrawn2017-02-17not published
Mohawk Solar
ID 0616
NYISO20Withdrawn2017-03-23not published
Monarda Solar
ID 0757
NYISO20Withdrawn2018-08-29not published

Where each number came from

Read this before quoting a figure. We re-read every source every week, but a weekly read of an unchanged file is not weekly data. These have not moved in a while: NYISO last changed 2026-07-16 (4 identical reads since). Those rows are exactly as current as the ISO's own published file, and no more.
ISOWe last readSource last changedSource
NYISO2026-08-062026-07-16 (unchanged across 4 weekly reads)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.

Interconnection queue home · This week's changes · How this is collected · US Tech Automations.