Interconnection queue › New York › Jefferson County › Solar
Solar Projects in Jefferson County, New York
Snapshot of 2026-09-07 · 17 projects
17 solar projects are in the interconnection queue in Jefferson County, New York, totaling 1,165 MW across the 17 that publish a capacity.
See what moved in solar in Jefferson County, New York each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in solar in Jefferson County, New York, from new entries to projects that came off the list.
Email me solar in Jefferson County, New York queue changesWork email only. No newsletter, no obligation.
By ISO
| ISO | Projects | Capacity |
|---|---|---|
| NYISO | 17 | 1,165 MW |
By fuel code, as published
| Fuel | Projects | Capacity |
|---|---|---|
| S | 17 | 1,165 MW |
By status, as published
| Status | Projects |
|---|---|
| Withdrawn | 12 |
| Active | 4 |
| Cluster Study | 1 |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| Bay Breeze Solar | NYISO | 200 | Withdrawn | 2021-12-20 | not published |
| Bay Breeze solar | NYISO | 150 | Cluster Study | 2024-09-20 | 12-2029 |
| NY38 Solar | NYISO | 120 | Active | 2019-05-29 | 04-2028 |
| Tracy Solar Energy Center | NYISO | 119 | Active | 2018-10-18 | 12-2028 |
| Rutland Center Solar | NYISO | 110 | Withdrawn | 2020-08-14 | not published |
| Thousand Island Solar | NYISO | 110 | Withdrawn | 2020-10-06 | not published |
| Riverside Solar | NYISO | 100 | Active | 2019-06-10 | 12-2027 |
| Honey Ridge Solar | NYISO | 80 | Withdrawn | 2020-08-11 | not published |
| Shaw Solar | NYISO | 20 | Withdrawn | 2017-08-01 | not published |
| Robinson Solar | NYISO | 20 | Withdrawn | 2017-08-01 | not published |
| Black Creek Solar | NYISO | 20 | Withdrawn | 2017-08-01 | not published |
| NY37 Solar | NYISO | 20 | Active | 2025-12-02 | 09-2028 |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| NYISO | 2026-09-07 | 2026-08-13 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.