Interconnection queue › New York › Madison County › Wind
Snapshot of 2026-08-06 · 15 projects
15 wind projects are in the interconnection queue in Madison County, New York, totalling 630 MW across the 15 that publish a capacity.
Get told what moves in wind in Madison County, New York
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in wind in Madison County, New York: what entered, what moved study phase, what came off the list.
Email me wind in Madison County, New York queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| NYISO | 15 | 630 MW |
| Fuel | Projects | Capacity |
|---|---|---|
| W | 15 | 630 MW |
| Status | Projects |
|---|---|
| Withdrawn | 13 |
| Active | 1 |
| Cluster Study | 1 |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| Hoffman Falls Wind 2 | NYISO | 102 | Withdrawn | 2022-02-24 | not published |
| Rolling Upland Wind Farm LLC | NYISO | 80 | Withdrawn | 2023-04-25 | not published |
| Stockbridge Wind | NYISO | 73 | Withdrawn | 2014-08-13 | not published |
| Rolling Upland Wind | NYISO | 73 | Withdrawn | 2015-12-03 | not published |
| Hoffman Falls Wind | NYISO | 72 | Active | 2021-01-27 | 04-2029 |
| Rolling Upland Wind | NYISO | 60 | Withdrawn | 2009-01-13 | not published |
| West Hill Windfarm | NYISO | 32 | Withdrawn | 2004-04-16 | not published |
| Hoffman Falls Wind 2 | NYISO | 30 | Cluster Study | 2024-08-01 | 12-2027 |
| Blue Hill Wind | NYISO | 25 | Withdrawn | 2020-11-24 | not published |
| Admiral Wind LLC | NYISO | 20 | Withdrawn | 2017-08-11 | not published |
| Cody Road | NYISO | 20 | Withdrawn | 2018-06-12 | not published |
| Cody Road Wind Farm | NYISO | 20 | Withdrawn | 2021-04-08 | not published |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| NYISO | 2026-08-06 | 2026-07-16 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.