Interconnection queue › New York › Montgomery County › Solar
Snapshot of 2026-08-06 · 16 projects
16 solar projects are in the interconnection queue in Montgomery County, New York, totalling 1,670 MW across the 16 that publish a capacity.
Get told what moves in solar in Montgomery County, New York
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in solar in Montgomery County, New York: what entered, what moved study phase, what came off the list.
Email me solar in Montgomery County, New York queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| NYISO | 16 | 1,670 MW |
| Fuel | Projects | Capacity |
|---|---|---|
| S | 16 | 1,670 MW |
| Status | Projects |
|---|---|
| Withdrawn | 12 |
| Active | 3 |
| Cluster Study | 1 |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| Taproot Solar Energy Energy | NYISO | 300 | Withdrawn | 2019-06-05 | not published |
| Taproot Solar | NYISO | 205 | Withdrawn | 2021-02-16 | not published |
| Flat Creek Solar | NYISO | 200 | Active | 2020-09-04 | 11-2028 |
| Amsterdam Solar | NYISO | 150 | Cluster Study | 2024-10-15 | 07-2028 |
| Cherry Valley Solar | NYISO | 125 | Withdrawn | 2022-09-07 | not published |
| OYA Fort Plain Solar | NYISO | 115 | Withdrawn | 2021-03-29 | not published |
| Yellow Feather Energy Center | NYISO | 110 | Withdrawn | 2022-12-22 | not published |
| Flat Creek Solar | NYISO | 100 | Active | 2020-11-23 | 11-2028 |
| Mohawk Solar | NYISO | 90 | Active | 2015-04-02 | 11/2027 |
| Tabletop Solar | NYISO | 80 | Withdrawn | 2019-06-04 | not published |
| Wintergreen Solar | NYISO | 75 | Withdrawn | 2021-02-16 | not published |
| East Light Energy Center | NYISO | 40 | Withdrawn | 2018-06-07 | not published |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| NYISO | 2026-08-06 | 2026-07-16 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.