Interconnection queue › New York › Queens County
Queens County, New York Interconnection Queue
Snapshot of 2026-09-07 · 63 projects · New York (NY)
There are 63 projects in the interconnection queue located in Queens County, New York (NY), totaling 16,362 MW across the 59 that publish a capacity.
Technology in Queens County
See what moved in Queens County, New York each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in Queens County, New York, from new entries to projects that came off the list.
Email me Queens County, New York queue changesWork email only. No newsletter, no obligation.
By ISO
| ISO | Projects | Capacity |
|---|---|---|
| NYISO | 63 | 16,362 MW |
By fuel, as published
Shown in each ISO's own coding. We do not merge two operators' spellings of the same technology here. The national table is the only place any fuel code is mapped.
| Fuel | Projects | Capacity |
|---|---|---|
| ES | 38 | 3,523 MW |
| W | 8 | 8,520 MW |
| CC | 5 | 967 MW |
| CT | 4 | 1,356 MW |
| DC | 2 | not published |
| D | 2 | 495 MW |
| AC | 2 | not published |
| NG | 1 | 500 MW |
| H | 1 | 1,000 MW |
By status, as published
| Status | Projects | Capacity |
|---|---|---|
| Withdrawn | 56 | 16,032 MW |
| Active | 7 | 330 MW |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| OW Ocean Winds East 5 | NYISO | 1,600 | Withdrawn | 2021-06-02 | not published |
| Queensboro Renewable Express Circuit A | NYISO | 1,310 | Withdrawn | 2022-12-21 | not published |
| Queensboro B | NYISO | 1,310 | Withdrawn | 2023-11-28 | not published |
| EI Steinway 1 | NYISO | 1,300 | Withdrawn | 2020-05-19 | not published |
| EI Steinway 2 | NYISO | 1,300 | Withdrawn | 2020-05-19 | not published |
| NY Interconnection 2 | NYISO | 1,200 | Withdrawn | 2021-06-18 | not published |
| Riverbank Power J | NYISO | 1,000 | Withdrawn | 2008-03-03 | not published |
| Benchmark Generator | NYISO | 900 | Withdrawn | 2007-12-20 | not published |
| Astoria Energy - Phase 2 | NYISO | 500 | Withdrawn | 1999-11-16 | not published |
| Astoria Annex Energy Storage | NYISO | 500 | Withdrawn | 2022-03-03 | not published |
| Luyster Creek Energy | NYISO | 401 | Withdrawn | 2011-02-15 | not published |
| Astoria Repowering-Phase 1 | NYISO | 367 | Withdrawn | 1999-07-13 | not published |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| NYISO | 2026-09-07 | 2026-08-13 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.