Interconnection queue › New York › Queens County › Storage
Storage Projects in Queens County, New York
Snapshot of 2026-09-07 · 38 projects
38 storage projects are in the interconnection queue in Queens County, New York, totaling 3,523 MW across the 38 that publish a capacity.
See what moved in storage in Queens County, New York each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in storage in Queens County, New York, from new entries to projects that came off the list.
Email me storage in Queens County, New York queue changesWork email only. No newsletter, no obligation.
By ISO
| ISO | Projects | Capacity |
|---|---|---|
| NYISO | 38 | 3,523 MW |
By fuel code, as published
| Fuel | Projects | Capacity |
|---|---|---|
| ES | 38 | 3,523 MW |
By status, as published
| Status | Projects |
|---|---|
| Withdrawn | 33 |
| Active | 5 |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| Astoria Annex Energy Storage | NYISO | 500 | Withdrawn | 2022-03-03 | not published |
| Battoria | NYISO | 300 | Withdrawn | 2021-06-21 | not published |
| Roma Storage | NYISO | 255 | Withdrawn | 2023-05-18 | not published |
| Roma Storage 2 | NYISO | 255 | Withdrawn | 2023-09-05 | not published |
| QMB2 Energy Storage, LLC | NYISO | 200 | Withdrawn | 2021-04-27 | not published |
| QMB2 Storage II | NYISO | 200 | Withdrawn | 2023-06-20 | not published |
| Ravenswood Energy Storage | NYISO | 187 | Withdrawn | 2018-12-20 | not published |
| Far Rockaway Energy Storage Center | NYISO | 150 | Withdrawn | 2019-10-11 | not published |
| Ravenswood Energy Storage 1 | NYISO | 129 | Withdrawn | 2018-03-09 | not published |
| Ravenswood Energy Storage 2 | NYISO | 129 | Withdrawn | 2018-03-09 | not published |
| Enel NYPA Astoria | NYISO | 100 | Withdrawn | 2019-10-18 | not published |
| Astoria Energy Storage | NYISO | 100 | Active | 2019-10-28 | 10-2026 |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| NYISO | 2026-09-07 | 2026-08-13 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.