Interconnection queueCalifornia › Hydro

Hydro Projects in the California Interconnection Queue

Snapshot of 2026-07-30 · 15 projects

15 hydro projects are in the interconnection queue with a California location, totalling 6,433 MW across the 15 that publish a capacity.

Grouped from the ISOs' own fuel codes — see the mapping. Codes we could not match to a published definition are left unclassified rather than assigned here.

Get told what moves in hydro in California

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in hydro in California: what entered, what moved study phase, what came off the list.

Email me hydro in California queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
CAISO156,433 MW

By status, as published

StatusProjects
WITHDRAWN11
ACTIVE2
COMPLETED2

Top counties

CountyProjectsCapacity
RIVERSIDE45,508 MW
TEHAMA36 MW
PLACER231 MW
SAN DIEGO140 MW
TUOLUMNE17 MW
HUMBOLDT140 MW
MENDOCINO140 MW
SAN LUIS OBISPO1650 MW
MARIPOSA1110 MW

Where each number came from

ISOWe last readSource last changedSource
CAISO2026-07-302026-07-30 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.

Interconnection queue home · This week's changes · How this is collected · US Tech Automations.