Interconnection queue › Massachusetts › Gas
Gas Projects in the Massachusetts Interconnection Queue
Snapshot of 2026-09-07 · 36 projects
36 gas projects are in the interconnection queue with a Massachusetts location, totaling 4,942 MW across the 25 that publish a capacity.
See what moved in gas in Massachusetts each week
The ISOs publish today's queue and overwrite it, so no archive exists. We keep a weekly copy. Leave your email and we'll send you each week's changes in gas in Massachusetts, from new entries to projects that came off the list.
Email me gas in Massachusetts queue changesWork email only. No newsletter, no obligation.
By ISO
| ISO | Projects | Capacity |
|---|---|---|
| ISO-NE | 36 | 4,942 MW |
By status, as published
| Status | Projects |
|---|---|
| (not published) | 36 |
Top counties
| County | Projects | Capacity |
|---|---|---|
| Worcester | 10 | 683 MW |
| Norfolk | 5 | -21 MW |
| Suffolk | 5 | 1,600 MW |
| Hampden | 4 | 9 MW |
| Middlesex | 4 | 154 MW |
| Plymouth | 3 | 1,308 MW |
| Bristol | 2 | 5 MW |
| Essex | 2 | 1,194 MW |
| Hampshire | 1 | 10 MW |
Largest projects with published capacity
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | County | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|---|
| Combined Cycle | ISO-NE | Plymouth | 898 | not published | 2/9/2009 | 3/1/2015 |
| Combined Cycle | ISO-NE | Suffolk | 800 | not published | 4/20/2020 | 6/1/2024 |
| Combined Cycle | ISO-NE | Suffolk | 800 | not published | 4/20/2020 | 6/1/2024 |
| Footprint Combined Cycle Unit | ISO-NE | Essex | 716 | not published | 1/13/2012 | 5/31/2018 |
| Simple Cycle | ISO-NE | Essex | 478 | not published | 2/24/2014 | 5/1/2018 |
| Combined Cycle | ISO-NE | Plymouth | 410 | not published | 10/16/2009 | 5/1/2015 |
| Gas Turbine | ISO-NE | Worcester | 188 | not published | 12/5/2008 | 6/1/2012 |
| Gas Turbine | ISO-NE | Worcester | 159 | not published | 5/15/2007 | 6/1/2013 |
| Gas Turbine | ISO-NE | Worcester | 159 | not published | 5/15/2007 | 6/1/2010 |
| Lowell Power Generators | ISO-NE | Middlesex | 99 | not published | 10/14/2005 | 6/1/2010 |
| Gas Turbine | ISO-NE | Worcester | 77 | not published | 1/29/2008 | 6/1/2011 |
| Cogen DG | ISO-NE | Middlesex | 43 | not published | 10/17/2016 | 9/30/2021 |
Where each number came from
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| ISO-NE | 2026-09-07 | 2026-09-07 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.