Interconnection queueTexas › Gas

Gas Projects in the Texas Interconnection Queue

Snapshot of 2026-07-30 · 140 projects

140 gas projects are in the interconnection queue with a Texas location, totalling 66,513 MW across the 140 that publish a capacity.

Grouped from the ISOs' own fuel codes — see the mapping. Codes we could not match to a published definition are left unclassified rather than assigned here.

Get told what moves in gas in Texas

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in gas in Texas: what entered, what moved study phase, what came off the list.

Email me gas in Texas queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
ERCOT11761,425 MW
SPP194,962 MW
MISO4126 MW

By status, as published

StatusProjects
SS Completed, FIS Started, No IA58
SS Completed, FIS Started, IA17
SS Started, FIS Started, No IA17
SS Completed, FIS Completed, IA13
IA FULLY EXECUTED/COMMERCIAL OPERATION12
SS Completed, FIS Completed, No IA6
Small Gen6
Withdrawn3
DISIS STAGE2
IA FULLY EXECUTED/ON SCHEDULE2
ERAS2
Done1

Top counties

CountyProjectsCapacity
Reeves94,602 MW
Bastrop73,822 MW
Ward62,268 MW
Pecos65,363 MW
Hale61,978 MW
Caldwell53,055 MW
Hays472 MW
Ellis4534 MW
Guadalupe4459 MW
Wilbarger33,156 MW
Harris3500 MW
Wharton31,452 MW
McLennan3223 MW
Jack33,207 MW
Grimes31,746 MW

Where each number came from

Read this before quoting a figure. We re-read every source every week, but a weekly read of an unchanged file is not weekly data. These have not moved in a while: ERCOT last changed 2026-06-11 (9 identical reads since). Those rows are exactly as current as the ISO's own published file, and no more.
ISOWe last readSource last changedSource
ERCOT2026-07-302026-06-11 (unchanged across 9 weekly reads)source file
MISO2026-07-302026-07-30 (changed this snapshot)source file
SPP2026-07-302026-07-30 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.

Interconnection queue home · This week's changes · How this is collected · US Tech Automations.