Interconnection queue › California › Kern County › Solar
Snapshot of 2026-08-06 · 236 projects
236 solar projects are in the interconnection queue in Kern County, California, totalling 36,401 MW across the 236 that publish a capacity.
Get told what moves in solar in Kern County, California
The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in solar in Kern County, California: what entered, what moved study phase, what came off the list.
Email me solar in Kern County, California queue changes →Work email only. No newsletter, no obligation.
Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.
| ISO | Projects | Capacity |
|---|---|---|
| CAISO | 236 | 36,401 MW |
| Fuel | Projects | Capacity |
|---|---|---|
| Solar | 236 | 36,401 MW |
| Status | Projects |
|---|---|
| WITHDRAWN | 181 |
| COMPLETED | 33 |
| ACTIVE | 22 |
The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.
| Project | ISO | MW | Status | Queue date | Proposed operation |
|---|---|---|---|---|---|
| CITY OF VERNON RENEWABLE PROJECT 2 | CAISO | 1,100 | WITHDRAWN | 2009-07-31 | not published |
| CENTRAL VALLEY I SEGS | CAISO | 1,080 | WITHDRAWN | 2011-03-31 | not published |
| KERN SOLAR RANCH (FKA CALIFORNIA SOLAR RANCH) | CAISO | 1,000 | WITHDRAWN | 2011-03-31 | not published |
| CALIFORNIA CITY SOLAR | CAISO | 700 | WITHDRAWN | 2016-05-02 | not published |
| PV-47 | CAISO | 700 | WITHDRAWN | 2008-05-06 | not published |
| PV-48 | CAISO | 700 | WITHDRAWN | 2008-05-06 | not published |
| PV-49 | CAISO | 700 | WITHDRAWN | 2008-05-30 | not published |
| EUISMOD | CAISO | 600 | ACTIVE | 2021-04-15 | not published |
| MARICOPA SOLAR | CAISO | 600 | WITHDRAWN | 2009-07-31 | not published |
| SANBORN 5 HYBRID | CAISO | 550 | ACTIVE | 2020-04-15 | not published |
| CENTRAL VALLEY II SEGS | CAISO | 540 | WITHDRAWN | 2011-03-31 | not published |
| WALLER SOLAR FARM | CAISO | 500 | WITHDRAWN | 2016-05-02 | not published |
| ISO | We last read | Source last changed | Source |
|---|---|---|---|
| CAISO | 2026-08-06 | 2026-08-06 | source file |
Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.