Interconnection queueCaliforniaKern County › Solar

Solar Projects in Kern County, California

Snapshot of 2026-08-06 · 236 projects

236 solar projects are in the interconnection queue in Kern County, California, totalling 36,401 MW across the 236 that publish a capacity.

Grouped from the ISOs' own fuel codes — see the mapping. Codes we could not match to a published definition are left unclassified rather than assigned here.

Get told what moves in solar in Kern County, California

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in solar in Kern County, California: what entered, what moved study phase, what came off the list.

Email me solar in Kern County, California queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
CAISO23636,401 MW

By fuel code, as published

FuelProjectsCapacity
Solar23636,401 MW

By status, as published

StatusProjects
WITHDRAWN181
COMPLETED33
ACTIVE22

Largest projects with published capacity

The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.

ProjectISOMWStatusQueue dateProposed operation
CITY OF VERNON RENEWABLE PROJECT 2
ID 505
CAISO1,100WITHDRAWN2009-07-31not published
CENTRAL VALLEY I SEGS
ID 803
CAISO1,080WITHDRAWN2011-03-31not published
KERN SOLAR RANCH (FKA CALIFORNIA SOLAR RANCH)
ID 680
CAISO1,000WITHDRAWN2011-03-31not published
CALIFORNIA CITY SOLAR
ID 1320
CAISO700WITHDRAWN2016-05-02not published
PV-47
ID 363
CAISO700WITHDRAWN2008-05-06not published
PV-48
ID 364
CAISO700WITHDRAWN2008-05-06not published
PV-49
ID 400
CAISO700WITHDRAWN2008-05-30not published
EUISMOD
ID 2055
CAISO600ACTIVE2021-04-15not published
MARICOPA SOLAR
ID 487
CAISO600WITHDRAWN2009-07-31not published
SANBORN 5 HYBRID
ID 1791
CAISO550ACTIVE2020-04-15not published
CENTRAL VALLEY II SEGS
ID 804
CAISO540WITHDRAWN2011-03-31not published
WALLER SOLAR FARM
ID 1315
CAISO500WITHDRAWN2016-05-02not published

Where each number came from

ISOWe last readSource last changedSource
CAISO2026-08-062026-08-06 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.

Interconnection queue home · This week's changes · How this is collected · US Tech Automations.