Interconnection queueCaliforniaStanislaus County › Solar

Solar Projects in Stanislaus County, California

Snapshot of 2026-08-06 · 18 projects

18 solar projects are in the interconnection queue in Stanislaus County, California, totalling 1,819 MW across the 18 that publish a capacity.

Grouped from the ISOs' own fuel codes — see the mapping. Codes we could not match to a published definition are left unclassified rather than assigned here.

Get told what moves in solar in Stanislaus County, California

The ISOs publish today's queue and overwrite it — no archive, no history. We keep a weekly copy. Leave your email and we'll send you what changed in solar in Stanislaus County, California: what entered, what moved study phase, what came off the list.

Email me solar in Stanislaus County, California queue changes →

Work email only. No newsletter, no obligation.

Prefer to just buy it? See the queue sentinel, priced, with last week's changes as a free sample.

By ISO

ISOProjectsCapacity
CAISO181,819 MW

By fuel code, as published

FuelProjectsCapacity
Solar181,819 MW

By status, as published

StatusProjects
WITHDRAWN14
COMPLETED3
ACTIVE1

Largest projects with published capacity

The 12 highest-capacity rows in this page's exact scope, ordered by the capacity the ISO published. Projects without a published capacity are not ranked here and remain included in the totals above.

ProjectISOMWStatusQueue dateProposed operation
BELTRAN SOLAR
ID 1118
CAISO300WITHDRAWN2015-04-30not published
PROXIMA SOLAR
ID 1244
CAISO300COMPLETED2016-05-02not published
NIKOVASTER
ID 1562
CAISO240WITHDRAWN2019-04-15not published
HOOD 2
ID 1452
CAISO200WITHDRAWN2018-04-16not published
HOOD 3
ID 1453
CAISO200WITHDRAWN2018-04-16not published
ROYAL SOLAR
ID 1281
CAISO102WITHDRAWN2016-05-02not published
GOLDWICK SOLAR FARM
ID 1377
CAISO101WITHDRAWN2017-05-01not published
STANISLAUS SOLAR
ID 832
CAISO75WITHDRAWN2011-03-31not published
GOLDEN HILLS SOLAR FARM
ID 707
CAISO70WITHDRAWN2011-03-31not published
JOAQUIN SOLAR
ID 1274
CAISO41WITHDRAWN2016-05-02not published
CENTRAL 40
ID 1103
CAISO40COMPLETED2015-04-30not published
FRONTIER SOLAR II (FKA SCATEC WESTSIDE SOLAR RANCH II)
ID 765
CAISO30WITHDRAWN2011-03-31not published

Where each number came from

ISOWe last readSource last changedSource
CAISO2026-08-062026-08-06 (changed this snapshot)source file

Compiled from each ISO's own published interconnection queue report. Queue position is not a permit, a contract, or a guarantee that a project will be built; most projects in every queue are eventually withdrawn. Figures are reproduced as published, are provided for informational purposes only, and carry no warranty of accuracy or completeness. Always verify against the ISO's own report before relying on any figure.